CU.ED.00.04- ditto
HCL still to construct solid balustrade to 1FL half landing. If not steel frame to HCL details then HCL to forward details for comment- Action HCL
CU.ID.02.16 door catching on tiles- now marked. Tile to be replaced, door raised to suitable height- Action HCL
Cunliffe coping GL G- poor pointing/ flashing. Rebed- Action HCL
Cunliffe coping GL A-B. Not as CVA detail. Specials not used as CVA/ Ibstock details. Remove and replace as CVA details. Action HCL
Ditto
HCL to confirm cill detail to CU.EW.02.11 as not as original CVA detail. Action HCL
Reveal detail not as CVA details. To be replaced. Action HCL
Bean LRC repairs still underway. All clips, cables etc. to be removed as CVA details.Action HCL
Ditto
Awnings installation underway to Cunliffe. Pressed metal head flashing still to be completed.- Action HCL
Brickshield to Cunliffe- GL A-B/ 1- brickshield poorly applied- finish and pointing inconsistent- remove and reapply- Action HCL
Damage adjacent RWP 2FL- remove damaged slips and reapply/ repoint- Action HCL
Tiles to roof still not mixed as per spec. - HCL to address- Action HCL
No soft joints to Brickshield as per CVA details CU 30.2, CU 30.3. Joints to be raked out and movement joint added as per drawings and specification. Action HCL
Perforate lining to Bean RL.01.01. Plasterboard misaligned RHS photo low level triangular reveal. Hole filling inconsistent with details. HCL to address- Action HCL
Ditto RL.01.03
Hard landscape underway adjacent Ashton building