Monday, 26 January 2015

Site visit 20+23.01.15

 Bean LRC overview

 Stage lawn not to be used for storage of materials. All to be removed and compound formed as tender documents
 Refectory opening formed poorly and damaged. To be rebuilt with sufficient framing/ strength

 Lining to Cunliffe top floor- CVA to confirm internal geometry

 Bulkhead lining construction underway- top floor Cunliffe classrooms

 Ditto

 Mortar applied to brickshield area- comparison with red mortar now apparent- acceptable constrast

 Brickwork repairs- further sample formed with dye- lower right area of image acceptable to client.

 Cunliffe 2FL opening formed for CU.ED.02.01. Upstand exposed to cill level.

  Cunliffe 2FL opening formed for CU.ED.02.01. Upper lintol to be repositioned to allow current opening to be retained
Bean LRC roof- interface between roof plant enclosure and parapet wall built incorrectly. HCL to refer
 4Bay to rectify height of brickwork support steelwork- set at incorrect height. HCL to advise

 Ditto

 Special cavity tray now installed to 1FL Bean LRC arched openings

 CVA to confirm support to cavity- Cunliffe drawings refer to metsec frame

 Ditto

 Cunliffe service risers- HCL builderswork openings not as OR builderswork. HCL to provide grille or appropriate guarding- HCL to advise/ confirm

 AC units to corridors. Bower Fuller to provide spigot connection details. CVA to update design intent in lieu of site fabricated upper panels.

 Cunliffe- GFL + 1FL soffit  repairs still to be carried out- M&E installation already in progress- works out of sequence. Care to be taken to protect or remove all equipment during making good works. CVA to monitor. HCL to forward method statement. Action HCL

 Window installation- Alucraft windows all include restrictor control obstructing proposed lining. Not included in drawings or commented on. Alucraft to forward alternative location/ control. HCL to confirm that fixings will be suitably sealed and hidden by linings in all locations. Action HCL

 HCL to provide insulation where timber reveal build out not solid. Air tightness detailing to be carried out to all windows/ reveals in both new build and refurb Cunliffe building. Action HCL

 First fix electrical services installed in Cunliffe in lieu of raised floor system. Areas to be cleared prior to installation. Action HCL
 Tile backer board used to both faces of sanitorium. Not as Specification K10/ 110F which stipulates 1 No. layer wallboard to outer face and tile backer board to inner face. HCL to address. Action HCL

Profile to be added over openings to Brickshield north elevation- Action HCL

Insulation setting out incorrect to 1FL reveals- HCL to advise how to address- Action HCL

Existing openings to be blocked up prior to application of further insulation- Cunliffe North elevation
-Action HCL
awaiting brickshield/ cill pressing- Cunliffe north elevation

Temporary waterproofing to roof of flat roof dormer/ awaiting windows/ pressed metal roof- Cunliffe north elevation

Internal partition to be formed between stair/ staffroom- Action HCL

Drylining to be added internal to line stairwell/ dormer- Action HCL

Roof tile sorting still to be reviewed- Cunliffe north elevation

Bauder roof ongoing- Bean LRC link

Cunliffe eaves detail to be completed in brickwork in lieu of brickshield insulation-  Action HCL

Window beads marked during transit/ lifting via forks to be installed. All future lifts to be with adequate protection. Existing beads to all be replaced where damaged. Action HCL

Ditto

Thursday, 15 January 2015

Site visit 15.01.15

 Overview- Bean LRC

 Arcade arch rebuilt- single skin. HCL to ensure mortar fill between when second skin added

 Arcade arches to be removed/ reset where too high

 Refectory servery opening formed

 Bean back stair precast unit still to be reset- note low first tread

 Cunliffe north elev- brickshield underway. HCL to advise programme for construction of brickshield below metal profile
Ditto

Arcade/ Cunliffe interface- external detail

Arcade/ Cunliffe interface- Internal joint unacceptable- too wide and not as sample panel- specials to be used to corner as CVA details
 
Ditto

 Intumescent paint added to Cunliffe steelwork

 Brickshield reveal detail- Cunliffe GFL

 Arch infill joint unacceptable as soft joint required. HCL to ensure consistent 10mm gap between arch and infill panel for mastic bead. Refer reference panel for brick cutting quality requirement

 CVA to advise of lining detail to Bean entrance lobby GFL

 brickwork prep GFL to Bean Refurb. CVA to advise regarding brick match where new bricks required

 Downpipe to be to show onto roof with outlet below, not as currently built

 Bauder roof to triangle roof area still required

 Unistruct to seminar stair ceiling

 Intumescent paint to steelwork Cunliffe

 Riser opening- full cutaway not required- HCL to provide infill grille or vertical guarding for fall protection.

2FL Cunliffe AHU where airtight ceiling. caulk required to interface between timber and boards.

 Bean link roof- awaiting insulation/ outlets
Cunliffe 2FL doorway opening onto roof also to be formed

Bean Plant steelwork now in situ

 Bean roof upstand- areas formed around scaffold. HCL to advise how these areas will be made good and form adequate substrate for Bauder membrane

 CVA to provide detail for upstand/ return to roof adjacent plant areas

 TV aerial containment. Insulation to be formed around where brickshield applied

 Bean Hall GFL- speaker containment. CVA to forward meeting notes with ESL to confirm AV equipment locations and containment routes/ fixings

Soft joint to brickshield- HCL to advise of location for soft joint if different from CVA drawings

Hit and miss brickwork- Cunliffe- HCL to adjust where coursing incorrect