Tuesday, 30 June 2015

Site visit 26.06.15

 Bean LRC 1st flr- Bulkhead to shadow recess incorrect GL 1/C- refer BE 7.1,

 Bean LRC 1st flr- as window has been set 1 brick too high there is now an issue with the grille and detail which deviate from CVA detail. Cill level to be 1m AFFL to ensure consistency with loose furniture. HCL to advise of revised grille size.
 Ditto
 Mould still very present 1FL Cunliffe- Action HCL

 Ditto

 Ditto

 Clash between curtain wall and capping detail- to be addressed alongside fitting of pressed metal capping detail/ when pressed metal flashings applied- Action HCL

 capping detail G/L 3/A- requires resin fill- also G/L 3/C. Flashings as H71 still to be applied. Action HCL


 Cunliffe 2fl window reveal CU.ED.02.01 brickshield incorrect. Whole cut bricks with solid return required to corners. mitred/ glued slips unacceptable- Action HCL 
Ditto

 Cunliffe steel balustrade 2FL- 4 Bay revised drawing still required showing proposed remedials. No drawing received since comments of 09.06.15. Steel infill undersized- Action HCL

 No temporary protection on any new doors or bespoke fitted joinery. Any damage will need to be made good/ items replaced- Action HCL

 Ditto

 Entire site strewn with rubbish making movement around site hazardous. Unacceptable- HCL to address- Action HCL
 Framing underway to underside of arcade- black neoprene spacer required as per standard trespa spec H20/ 155A
 Ditto

 Insulation required to underside of soffit- link

 Infill panels required above long precast beam to Bean Hall GFL. Coffers with ducts can be exempt as covered in perforated panelling. Fixing can be discussed/ sketched by CVA if required- Action HCL

 Bean LRC lobby bulkhead soffit to be removed and set at correct height- Action HCL

Marshalls office- screen removed in error. HCL to reconstruct and fit - Action HCL

 Detail of screen to match adjacent doors

 Making good of strair drylining required Bean LRC- Action HCL


  Ditto acoustic/ fire protection. Stringer/ skirting to stair to be consistent with arris- Action HCL


 Bean LRC perimeter ceiling detail 1FL- drylining around steel required locally within reveal- Action HCL



 Librarians office- plasterboard/ plaster incomplete behind dado- Action HCL
Ditto

 Ditto
 cill/ EDPM to be addressed BE.EW.01.08- Action HCL


 Plasterwork/ taping and jointing poor 1FL classrooms- Action HCL


Bean rooflights- airtightness detailing poor- Action HCL


Level of glazing to pyramid rooflights in relation to slate roof not as CVA details or Alucraft details C629-D112-4. HCL to advise

Airtightness details to be carried out internally prior to glazing- Action HCL


Awaiting grilles to plantroom enclosure. Upper level flashing to be addressed once installed- Action HCL


Trespa fitted to classroom block entry- no neoprene installed - Action HCL

Ditto- Action HCL

Monday, 15 June 2015

Site visit 12.06.15

 Bean Seminar stair- awaiting secondary ceiling frame

 Arch return adjacent Cunliffe- brick/ mortar still to be made good/ addressed- not as reference panel

 Awaiting soffit panelling to interface between arches and link

 Brickshield to Cunliffe under link- profile carrying cladding bent- to be adjusted before final insulation/ slips applied- Action HCL
 Ditto.Also ensure adequate space for build up of sub base, mortar bedding and slab- Action HCL

Bean refurb- arch removed in error due to be rebuilt

Bean LRC overview

Arcade awaiting panelling, rooflights and landscape. Brick remedials/ cleaning  still to be carried out- Action HCL
RWP now moved to allow clearance for soffit cladding panels in trespa

Relocated radiator/ dado acceptable in Marshall's room. Allowance for 1400 desk

Water fountain to be installed at 900mm AFFL. Currently installed at 1000 AFFL- Action HCL

Brick wall underway to modified window opening BE.EW.00.11- Action HCL

Ceiling to stop short in lieu of archive display joinery- Action HCL

Precast concrete soffits to Bean Hall now with lights installed. Awaiting acoustic panels and perforated metal panels- Action HCL

Interface between precast concrete stair and slab. Acoustic and fire rated partition/ soffit to be formed. Cannot be achieved with bulkhead to be built beneath.- Action HCL

Servery duct rising onto roof avoiding 1FL roof gulley. Additional fire rated compartment to be formed to ceiling.- Action HCL
All redundant cables to be removed- Action HCL

Bean LRC 1st FLR overview

Laminate doors still not protected- Action HCL

Steel frame glazed doors unprotected- Action HCL

Acoustic panels installed 1st floor Cunliffe

Metal hatches installed 1st + 2nd floor Cunliffe

Cunliffe 2FL staff room- remedial works required to walls- Action HCL

Ventilation joinery panel installation underway 2FL- Action HCL

Cunliffe brickshield to Cunliffe 2FL adjacent link still to be carried out- Action HCL

Cunliffe laminate doors 2FL- unprotected and now marked- Action HCL

Slot drain installed to BE.ED.00.07

Now awaiting storm proof louvre installation

Bolt to Cunliffe stair crooked- ensure adequate fixing- Action HCL

Face fixed smoke head installed to Cunliffe rooflight 2FL