Pointing still to be carried out to arches- not continuous as previously raised
Pointing to parapet ongoing to Bean arcade
Mastis required to arches and completion of all fineline trims
Ditto
Movement joint- mastic to parapet to be completed
Cunliffe tile sorting still unacceptable as previous comments
Awaiting carpet and metal paneling to Bean Hall
Joinery installed to Bean GFL cloakroom
HCL to address poor interface with drylining in this location
Replacement door fitted to Bean LRC refurb Marshalls office
Concrete to kerb incorrect- HCL to address
Ditto
Capping to be mitred to corners as per Ibstock details
Ditto
Ditto
All manhles to be refitted with inset type as specified. Current covers temporary only. HCL to advise when switch will occur and provide comprehensive schedule as requested
Cunliffe south elevation. Glazed brick repaired but pointing to trespa to be removed
Final Cunliffe remedials underway
Bean/ Cunliffe brickwork interface still unacceptable as raised previously- HCL to address
Cunliffe hit and miss- mastic poor quality workmanship- replace
Ditto
Gas pipe to be painted in Umbra grey