Tuesday, 15 September 2015

site visit 10 + 11.09.15

 Bean seminar stair- making good/ decorations underway. Awaiting trim to perimeter of fire rated windows
 Pointing still to be carried out to arches- not continuous as previously raised

 Pointing to parapet ongoing to Bean arcade

 Mastis required to arches and completion of all fineline trims

 Ditto

 Movement joint- mastic to parapet to be completed

 Cunliffe tile sorting still unacceptable as previous comments

 Awaiting carpet and metal paneling to Bean Hall

 Joinery installed to Bean GFL cloakroom

 HCL to address poor interface with drylining in this location

 Replacement door fitted to Bean LRC refurb Marshalls office

 Concrete to kerb incorrect- HCL to address

Ditto

 Capping to be mitred to corners as per Ibstock details

Ditto 

 Stage lawn to be repaired as damaged during construction as not adequately protected. Lime mortar repairs only. All at HCL's cost

 Ditto

 All manhles to be refitted with inset type as specified. Current covers temporary only. HCL to advise when switch will occur and provide comprehensive schedule as requested

 Cunliffe south elevation. Glazed brick repaired but pointing to trespa to be removed

 Final Cunliffe remedials underway

 Bean/ Cunliffe brickwork interface still unacceptable as raised previously- HCL to address

 Cunliffe hit and miss- mastic poor quality workmanship- replace

Ditto

Gas pipe to be painted in Umbra grey

 Reference panels to now be removed

Tuesday, 8 September 2015

Site visit 28.08.15

 Cunliffe remedials ongoing- library square underway

Ditto

 
Ditto

 CVA to check flashing spce to roof

 Arch view of monument

 Cappings to extend over gap between Bean/ Cunliffe where water ingress possible

 Bean arcade- louvre to be replaced

 Remedials required to new arch feature- Old Bean refurb


Brick remedials still required to Bean

 Cloakroom GFL Bean underway. Head to inset lockers to be resolved

 Bean Refub GFL- decorations underway. Marshalls new screen to be fitted

Awaiting skirting/ oak flooring to seminar stair

 trims required to fire rated window required where detail poor

 Arcade rooflight glass to be replaced

 Panel damaged to north elevation arches

 Ditto plaster to west elevation arches

 Address Bean 1FL rooflight linings as previous comments

 Ditto

 Brickwork to be made good adjacent oak door lining 1FL Bean refurb

 Trim detailing pooor to Cunliffe stair acousit ceiling- HCL to address. Also not as CVA details
 Ditto acoutic panel/ timber trim not as CVA details

 Trim/ surround/ setting out/ cill lining still to be completed to Cunliffe 2FL acoustic vent

 Switches to plant artea to roof to be relocated to location as discussed with CVA- hidden from view

 Cowl setting detail to be addressed by Bower Fuller

Flooring infill required to 2FL Cunliffe stair