Thursday, 24 April 2014

Site Visit 23.04.14

Cunliffe 2Fl demi-dec installation complete- awaiting structural topping

Cunliffe 2FL existing structure demolition underway

Cunliffe 2FL- preparation for reinforcement of demi-dec

Bean LRC 1FL- grouting of joints to Double T slabs prior to structural topping

Old Bean- Excavation for goalpost frame

Overview of site

Goalpost frame components on site awaiting installation

Double T sections installed and grouted over precast beam. Radius finish and grout joint good.

Ditto

Column made good and grouted to beam. Further making good may be required in this area

Reinforcement for support structure for seminar stair elements

Ditto

Cunliffe 2FL demi-dec installed. Stairs/ landings to follow

Cunliffe 2FL demi-dec- marking out for reinforcement

Cunliffe 2FL- interface with insitu column- possible coverage issues to perimeter- HCL to address

Ditto

Ditto

Overview from Cunliffe Scaffold to Bean 1FL

Bean LRC 1FL reinforcement for insitu concrete slab

Bean LRC hall- column head grouted- awaiting rub down

Concrete footing to goalpost frame to Old Bean GFL

View of Bean LRC 1FL from old Bean (New opening to be formed)

Ditto
HCL to check provision for arch sample- refer HRW prop details 968/ sk002- Action HCL

Tuesday, 15 April 2014

Site Visit 09.04.14

Temporary propping in preparation for double T precast concrete slabs to Bean LRC Hall

 Precast column made good- awaiting beam/ grout. Top surface still unlevel

 Further making good to column

 Pitting and making good to column G/L B/2- still poor

  Pitting and making good to column gridline C/ 2

 G/L C-D/ 2- making good to precast column poor

 Temporary support underway

 Ditto

 Reinforcement for concrete support wall to seminar stair

 CVA to forward information of remedial works required to concrete wall  G/L C

 Footing cast for picture frame to Bean LRC refurb

Pad cast for steelwork to Bean LRC refurb G/L B-C

 Cunliffe- ground floor half landing cast- East stair

 Cunliffe First floor landing cast- East stair

 Cunliffe 1st floor- falsework under construction for insitu columns

 Overview- Cunliffe to Bean LRC

Cunliffe 1st floor

 Cunliffe East Stair

Scaffold erected around Bean LRC refurb section

Monday, 7 April 2014

Site visit 03.04.14

 Damage to precast beam from CCP- to be made good

 Site overview

 Naylor Lintols on site for Cunliffe openings

 CCP Precast beams for hall G/L 2

 Discrepancy to concrete wall G/L C
 Defective head to CCP columns to G/L 2- CCP to make good

 Ditto

 Ditto

 Cunliffe- 1st floor slab poured

 Ditto
 Reinforcement for 1Fl columns

 Reinforcement for 1FL landing

 Reinforcement for insitu half landing

Flexcell Interface between new build and existing Cunliffe slab

 Overview of Bean LRC

 Overview of Cunliffe stair

 Awaiting formwork/ concrete where gable removed to Cunliffe

 Existing Bean- excavation for footing to new inserted steelwork

 excavation for goalpost to old Bean G/L 4

 Setting out of landing to bean stair- HCL to check level

 Underside of Cunliffe 1FL slab precast panels is clean following pour

 Ditto

 HRW to check set out of kickers/ walls supporting seminar stair precast elements

Opening formed to old Bean- temporary support

 Columns G/L 2- defective finish to head to be made good

Cunliffe stair- awaiting pour of landing.