Underway
Bean BE.EW.00.06 Fineline frame detail poor- Action HCL
Ditto
Bean 1FL- still awaiting cavity tray installation to squint wall- Action HCL
Cunliffe gable bricks- brick broken- overflow to be added- Action HCL
Resin to be added under capping bricks- Cunliffe gables- Action HCL
Cunliffe gables- making good around cappings
Scaffold Struck to Bean- brickwork to be cleaned down- cappings/ movement joints adjusted
Bean GFL Arch BE.EW.00.07- soft joint to be added
Bean Refurb GFL- Dado overcladding in plasterboard- no flush skirting as CVA detail 0331sk623. Action HCL
Bean 1FL kitchen duct riser- BF to revise kitchen extract unit and confirm duct size.
Builderswork not aligned with partition- 400x400 duct will not fit. Revised aspect to be proposed. To penetrate at roof level out of the gutter. Condensate wastes to also be adjusted.
Cunliffe dormer cladding- aluminium side cladding not as drawing- diagonal sheeting/ no weathering detail. To be addressed. Also insulation face cladding/ soffit drip to be adjusted.- Action HCL
Mock up AC panels on site 2FL Cunliffe
Cavity tray/ducting GFL Cunliffe still to be amended- Action HCL
Door/ window screen adjusted Cunliffe GFL CU.ED.00.04+8
MF frame installed GFL Cunliffe exam room
Ditto
Cunliffe GFL- CU.00.07 Lobby handwash ceiling- insulation to ductwork to be addressed.
Cunliffe 1FL- ensure airtightness to all walls- Action HCL
Ditto
Bean GFL brickwork- movement joint required to plinth capping to align with wall MJ
GFL Bean Hall- Grilles to be installed for return air within double T beams
Fire stopping to Old Bean services penetration 1FL- Final ceiling level below corbel
Bean seminar stair- sail blind to be fixed to area adjacent vertical steel forming pyramid
Bean refurb- brick reveal refurb underway
Ditto
Bean 1FL overview
Capping cracked to Bean 1FL window BE.EW.01.08- HCL to address
Capping 1FL Bean arcade adjacent Cunliffe- gap formed between two
Ditto- cutaway required. HCL to ensure DPC lapped up
Beam decoration required- Action HCL
Ditto- CVA to confirm colour
Cunliffe 1FL- bulkhead projects due to electrical services- CVA request that this be brought in line with column projecting adjacent and shallower bulkhead continued above.- Action HCL
Bead now installed 2FL where wobbly plaster line- Cunliffe
Cunliffe dormer- window installed in correct position. Stud and linings to be amended accordingly- Action HCL
Ditto
Awaiting link glazing following scaffold strike
Soakaway installed- library square
Bean scaffold struck- clean down/ making good to follow- Action HCL