Brickwork GFL Cunliffe South Elevation.The marks to the cut header bond bricks have yet to be cleaned satisfactorily. This issue was raised first on 08.08.14. This brickwork is now condemned- notice to be forwarded to HCL. Locations to be rebuilt as follows: Cunliffe GL 7/F-G, GL 7/A-B
RIW LAC being applied to New Bean LRC GFL
Concrete remedials incomplete. Possible reinforcement exposed GL D/ 2-3 soffit level
Concrete remedials incomplete. Possible reinforcement exposed column GL D/ 2-3
Scabbling incomplete. Concrete remedials carried out where concrete frame is defective and has not been addressed. Scabbling to be carried out to ensure compliance with specification tolerances. This will affect internal finishes and must be addressed now. If reinforcement is exposed this will have to be addressed. Concrete frame condemned GL D/1 adjacent BE.EW.01.04.- notice to be forwarded to HCL.
RWP outlet positions to Bean LRC roof have been relocated on site to avoid structural ties. HCL to liaise with Bower Fuller via M&E coordinator to ensure any additional bends/ pipes/ access can be accommodated within services zone.
Cunliffe brickshield. 1st course of slips now applied low level. HCL to ensure undulations of insulation etc. are taken out within laying of slips to maintain flush finish as control sample.
Additional amendments to structure may be required to existing openings where head lowered and vault reinstated. CVA/ HRW to forward details where required.
Ditto
Bean roof refurb- VCL and insulation laid
Bean LRC roof- pyramids formed over steelwork to create rooflight lanterns.
HCL to address undulation in 4Bay steel to velux modular rooflight enclosure
Bauder VCL applied
Ponding to roof GL 1 may require insulation to be tapered to ensure adequate
Rooflight enclosure to seminar stair. Ply to be adjusted to ensure plane is continuous and allows for insulation to be applied without modification
Cunliffe stair walls currently under construction in blockwork
Builderswork to be adjusted locally where discrepancy with survey for height of existing beam to Cunliffe GL2-4/ D-E to wall of plantroom. CVA to instruct
Ceiling height to be adjusted to ITSS office to accommodate services where discrepancy to survey of 50mm- CVA to instruct
Ditto