Arch former to relief arch removed, infill brickwork commenced GL D
Stack bonded facing brick to parapet completed in lieu of capping GL D
Reference panel for brickshield commenced- awaiting completion/ pointing- Action HCL
East Arcade brickwork piers commenced
Bean structural ties to be removed for installation of airtight ceiling and drops- to be reinstated below within services zone- Action HCL
Bean roof refurb- VCL + insulation now installed- awaiting felt/ batten prior to tiling.
Cunliffe south elevation brickwork still at GFL. Lintols on site as of w/e 09.10.14. Brickwork has not been cleaned where cutting issue raised on 08.08.14 and due to be inspected on 14.08.14- Action HCL
Studwork commenced GFL. Sheetseal applied to GFL slab
studwork to stair- CVA to resolve stud discrepancy issue- Action CVA
1st layer Bauder applied to main roof deck Bean LRC. Steelwork to Modular rooflight to be adapted due to discrepancy of welded top plate. 4 Bay to attend to rectify- Action HCL
Awaiting completion of rooflight enclosure Bean LRC
1st layer bauder over projecting steel plate/ bolts. CVA to check detail with Bauder
Cunliffe 2FL- depth of parition to be adjusted to accommodate cross bracing internally- Action CVA
Brickshield recommenced to Cunliffe GFL
Cunliffe brickshield recommenced
Concrete arch remedials carried out 1FL Bean
Ditto
Ditto GL/ A- BE.EW.01.10. Tolerances likely to be outside requirements. HCL to review in lieu of arch window installation
Concrete remedials Cunliffe- underway.
1FL demi dec repair still required Cunliffe
Cunliffe roof valley tiling underway
Bauder valley now complete.
Awaiting flashing to parapet GL/ G
Ditto
Awaiting outlet installation to gutters Cunliffe roof
Valley lead/ saddle installation underway to Cunliffe roof dormers
CVA to instruct lining detail to GFL Bean refurb over damaged tiling- Action CVA
M&E tray installation underway to Cunliffe