Monday, 27 October 2014

Site visit 24.10.14

 Bean LRC overview

 Arch former to relief arch removed, infill brickwork commenced GL D

 Stack bonded facing brick to parapet completed in lieu of capping GL D

 Reference panel for brickshield commenced- awaiting completion/ pointing- Action HCL

 East Arcade brickwork piers commenced

 Seminar stair concrete- infill blockwork still required below bottom step- Action HCL

Bean structural ties to be removed for installation of airtight ceiling and drops- to be reinstated below within services zone- Action HCL

 Bean roof refurb- VCL + insulation now installed- awaiting felt/ batten prior to tiling.

Cunliffe south elevation brickwork still at GFL. Lintols on site as of w/e 09.10.14. Brickwork has not been cleaned where cutting issue raised on 08.08.14 and due to be inspected on 14.08.14- Action HCL

Studwork commenced GFL. Sheetseal applied to GFL slab

 studwork to stair- CVA to resolve stud discrepancy issue- Action CVA

1st layer Bauder applied to main roof deck Bean LRC. Steelwork to Modular rooflight to be adapted due to discrepancy of welded top plate. 4 Bay to attend to rectify- Action HCL

 Awaiting completion of rooflight enclosure Bean LRC

 1st layer bauder over projecting steel plate/ bolts. CVA to check detail with Bauder

 Cunliffe 2FL- depth of parition to be adjusted to accommodate cross bracing internally- Action CVA

 Brickshield recommenced to Cunliffe GFL

 Cunliffe brickshield recommenced

 Concrete arch remedials carried out 1FL Bean

 Ditto

 Ditto GL/ A- BE.EW.01.10. Tolerances likely to be outside requirements. HCL to review in lieu of arch window installation

 Concrete remedials Cunliffe- underway.

 1FL demi dec repair still required Cunliffe

 Cunliffe roof valley tiling underway

 Bauder valley now complete.

 Awaiting flashing to parapet GL/ G

 Ditto

 Awaiting outlet installation to gutters Cunliffe roof

 Valley lead/ saddle installation underway to Cunliffe roof dormers

 CVA to instruct lining detail to GFL Bean refurb over damaged tiling- Action CVA

M&E tray installation underway to Cunliffe

No comments:

Post a Comment