Tuesday, 8 July 2014

Site Visit 03.07.14

 Arch reference panel nears completion

 Ditto

 Awaiting vertical soldier course

 CVA to forward comments on other completed reference panels

 Overview of concrete frame

 drain unprotected- broken G/L 1/D

 Temporary support now installed to concrete frame

 Scabbling underway. HCL still to forward schedule of concrete remedials

 Concrete infill to double T beams still to be carried out

 Openings to be adjusted to Bean G/L 4. HRW to instruct additional steel support.
Special bricks to be provided to reveals- central mullion to be removed/ supported

 render to be removed and seminar stair wall reviewed.

 Class 1 red mortar silo on site

 HCL to advise where adjustments are to be made where steel frame may clash with localised variation due to concrete cover adjustment to downstand- HCL to advise

 BE.RWP.09 also unprotected and broken. HCL to advise of remedial work to address

 Common brick laid below DPC where below hard landscape levels

 West stair precast now fitted
 Voids formed to East stair for light fittings

 Overview of concrete frame

 Reinforcement projecting/ exposed to BE.EW.01.09

 Temporary support

Scabbling to arch in lieu of remedials BE.EW.01.03