Internal arcade arches incorrectly set-out. 3 No. to be rebuilt from spring-point.
Stud partitions underway to GFL Bean LRC
Tray installation commenced to Bean LRC Hall GFL
Lift pit to be drained.
Library cloak areas GFL Bean LRC
1FL Bean LRC. Airtight ceiling plasterboard to be replaced where panels damaged by water ingress.
M&E coordinator to forward drawing of overlay of 1200 grid of unistrut/ structural ties/ mechanical plant
Ditto
Velux modular rooflight installed
Concrete infill proposals acceptable- HCL to carry out
Brick/ block detail discussed with bricklayer. Cavity to be continuous
Bean LRC 1FL overview
Cunliffe CU.01.20 walls to stairwell to be lined- plasterboards to be dabbed on. grout to be chipped away carefully high level.
Cunliffe 2FL insulation. All insulation to be secured, gaps taped etc. to ensure U values achieved, continuity achieved.
Brickshield ongoing to Cunliffe GFL
CVA to review provision for fireproofing of steel and instruct accordingly
Setting out of radiators discussed with Bower Fuller. Disabled cubicles CU.00.10 and CU.01.13 incorrectly set out- space provision inadequate- Vales to adjust partitions accordingly to CVA setting out
Grout now added GL D 1FL Bean LRC where required.
Cunliffe Hit and miss now built in solids. Remedials still to be carried out where incorrect
1FL Cunliffe brickshield ongoing
Cunliffe South Elevation overview. Brickwork at mid 1FL level. HCL to ensure adequate ties added as specified
Bean Refurb roof. Gutter level/ projection to be confirmed following installation of insulation
Flashing to pitched dormer/ valley detail
Soaker installation complete- awaiting flashing
Bean LRC roof- Bauder/ outlet levels/ pooling to be addressed with lower level insulation around outlet.
Ditto
Green Bauder installation commenced. Rooflight covering/ slate etc. still to be completed.