Friday, 28 November 2014

Site visit 26.11.14

 Arch formers to lawn stage. All formers to be removed and herras fence reinstated as site set-up drawing to avoid damage of built fabric

 Internal arcade arches incorrectly set-out. 3 No. to be rebuilt from spring-point.

 Stud partitions underway to GFL Bean LRC

 Tray installation commenced to Bean LRC Hall GFL

 Lift pit to be drained.

 Library cloak areas GFL Bean LRC

 1FL Bean LRC. Airtight ceiling plasterboard to be replaced where panels damaged by water ingress.
 M&E coordinator to forward drawing of overlay of 1200 grid of unistrut/ structural ties/ mechanical plant

 
 Ditto


 Velux modular rooflight installed

 Concrete infill proposals acceptable- HCL to carry out

 Brick/ block detail discussed with bricklayer. Cavity to be continuous

 Bean LRC 1FL overview

 Cunliffe CU.01.20 walls to stairwell to be lined- plasterboards to be dabbed on. grout to be chipped away carefully high level.

 Cunliffe 2FL insulation. All insulation to be secured, gaps taped etc. to ensure U values achieved, continuity achieved.

 Brickshield ongoing to Cunliffe GFL

CVA to review provision for fireproofing of steel and instruct accordingly

Setting out of radiators discussed with Bower Fuller. Disabled cubicles CU.00.10 and CU.01.13 incorrectly set out- space provision inadequate- Vales to adjust partitions accordingly to CVA setting out
Grout now added GL D 1FL Bean LRC where required.

Cunliffe Hit and miss now built in solids. Remedials still to be carried out where incorrect


1FL Cunliffe brickshield ongoing

Cunliffe South Elevation overview. Brickwork at mid 1FL level. HCL to ensure adequate ties added as specified

Bean Refurb roof. Gutter level/ projection to be confirmed following installation of insulation

Flashing to pitched dormer/ valley detail

Soaker installation complete- awaiting flashing

Bean LRC roof- Bauder/ outlet levels/ pooling to be addressed with lower level insulation around outlet.

Ditto

Green Bauder installation commenced. Rooflight covering/ slate etc. still to be completed.

Thursday, 20 November 2014

Site Visit 19.11.14

Continued water Ingress affecting recently completed screed finishes

 Significant water ingress through to ground floor where screeding being carried out

 Screed wet with rainfall to GFL Bean LRC

 Studwork constructed in wet areas Bean LRC GFL

Builderswork to BE.00.03 service penetrations to be away from arch to upper LHS corner

Builderswork through Beam to BE.00.14 to be moved as far to LHS as possible. CVA to instruct additional bulkhead for services adjacent wall to existing Bean stair GFL

HRW to confirm builderswork allowances to GFL beams to old Bean refurb adjacent south elevation high level

Bower Fuller to introduce additional containment to access roof void in main roof Bean refurb, avoiding location of retractable projector screen

Bower Fuller to introduce additional containment to access roof void in smaller roof void in Bean refurb adjacent velux, beyond hatch location

 Bean refurb roof awaiting tiling

Site debris on most scaffold areas- to be cleared- Action HCL

 Ponding to gutter area to main Bean LRC roof. HCL to advise

 Ditto

Ditto

 Ditto

 Velux modular rooflight installed

 Metsec requires addional profile to extend to 200mm so internal walls flush as CVA comments

 Stud partition Cunliffe GFL CU.00.16- set out out of plumb. CONDEMNED. Hutton to rebuild

Cunliffe hit and miss brickwork vent panel constructed without solids as specified. Also opening not yet formed internally therefore built out of correct sequence. CONDEMNED.To be rebuilt- Action HCL

 Ditto- to be rebuilt in solids as specification and details. Soft joint correct.CONDEMNED. To be rebuilt- Action HCL

 GL 4/A 1FL- replace 2 No. stretchers damaged- To be rebuilt- Action HCL

Cunliffe GFL GL G/1- brickshield low level not yet completed and soon inaccessible- HCL to ensure brick slips and insulation go below profile also in this area- Action HCL

 RWP pipework- HCL to ensure coordination where rwp outlet locations altered and additional bends added- Action HCL
Scabbling still has not been carried out to concrete  reveal to BE.EW.01.04 despite assurances that this would be carried out BEFORE brickwork commenced at first floor level (refer email correspondence). Former now in place. Concrete out of required tolerances as Engineers specification. CONDEMNED- Action HCL.

 Ditto. CONDEMNED- Action HCL

  Ditto. CONDEMNED- Action HCL

 Air tight ceiling lining underway to Bean LRC 1FL. However building is not watertight and new linings are already wet. CONDEMNED. remove and make watertight before rebuilding.- Action HCL

 Ditto. CONDEMNED.- Action HCL

 1FL Bean LRC not watertight. Rooflights incomplete and unfinished. Works out of sequence.

 Drylining to Cunliffe Mechanical riser 1. Diamond drilling of slab carried out after drylining. All boards damaged. CONDEMNED. remove and replace.- Action HCL
  Rubble to many areas on site. Site to be cleared and tidied. Note dampness to plasterboards. CONDEMNED. remove and replace.- Action HCL

 1FL Cunliffe- classroom CU.01.07. Water ingress still apparent.

Water ingress to GFL plant area. This area must be watertight, clear and secure before any mechanical or electrical installations commence.