Significant water ingress through to ground floor where screeding being carried out
Screed wet with rainfall to GFL Bean LRC
Studwork constructed in wet areas Bean LRC GFL
Builderswork to BE.00.03 service penetrations to be away from arch to upper LHS corner
Builderswork through Beam to BE.00.14 to be moved as far to LHS as possible. CVA to instruct additional bulkhead for services adjacent wall to existing Bean stair GFL
HRW to confirm builderswork allowances to GFL beams to old Bean refurb adjacent south elevation high level
Bower Fuller to introduce additional containment to access roof void in main roof Bean refurb, avoiding location of retractable projector screen
Bower Fuller to introduce additional containment to access roof void in smaller roof void in Bean refurb adjacent velux, beyond hatch location
Bean refurb roof awaiting tiling
Site debris on most scaffold areas- to be cleared- Action HCL
Ponding to gutter area to main Bean LRC roof. HCL to advise
Ditto
Ditto
Ditto
Velux modular rooflight installed
Metsec requires addional profile to extend to 200mm so internal walls flush as CVA comments
Stud partition Cunliffe GFL CU.00.16- set out out of plumb. CONDEMNED. Hutton to rebuild
Cunliffe hit and miss brickwork vent panel constructed without solids as specified. Also opening not yet formed internally therefore built out of correct sequence. CONDEMNED.To be rebuilt- Action HCL
Ditto- to be rebuilt in solids as specification and details. Soft joint correct.CONDEMNED. To be rebuilt- Action HCL
GL 4/A 1FL- replace 2 No. stretchers damaged- To be rebuilt- Action HCL
Cunliffe GFL GL G/1- brickshield low level not yet completed and soon inaccessible- HCL to ensure brick slips and insulation go below profile also in this area- Action HCL
RWP pipework- HCL to ensure coordination where rwp outlet locations altered and additional bends added- Action HCL
Scabbling still has not been carried out to concrete reveal to BE.EW.01.04 despite assurances that this would be carried out BEFORE brickwork commenced at first floor level (refer email correspondence). Former now in place. Concrete out of required tolerances as Engineers specification. CONDEMNED- Action HCL.
Ditto. CONDEMNED- Action HCL
Ditto. CONDEMNED- Action HCL
Air tight ceiling lining underway to Bean LRC 1FL. However building is not watertight and new linings are already wet. CONDEMNED. remove and make watertight before rebuilding.- Action HCL
Ditto. CONDEMNED.- Action HCL
1FL Bean LRC not watertight. Rooflights incomplete and unfinished. Works out of sequence.
Drylining to Cunliffe Mechanical riser 1. Diamond drilling of slab carried out after drylining. All boards damaged. CONDEMNED. remove and replace.- Action HCL
Rubble to many areas on site. Site to be cleared and tidied. Note dampness to plasterboards. CONDEMNED. remove and replace.- Action HCL
1FL Cunliffe- classroom CU.01.07. Water ingress still apparent.
Water ingress to GFL plant area. This area must be watertight, clear and secure before any mechanical or electrical installations commence.