Thursday, 20 November 2014

Site Visit 19.11.14

Continued water Ingress affecting recently completed screed finishes

 Significant water ingress through to ground floor where screeding being carried out

 Screed wet with rainfall to GFL Bean LRC

 Studwork constructed in wet areas Bean LRC GFL

Builderswork to BE.00.03 service penetrations to be away from arch to upper LHS corner

Builderswork through Beam to BE.00.14 to be moved as far to LHS as possible. CVA to instruct additional bulkhead for services adjacent wall to existing Bean stair GFL

HRW to confirm builderswork allowances to GFL beams to old Bean refurb adjacent south elevation high level

Bower Fuller to introduce additional containment to access roof void in main roof Bean refurb, avoiding location of retractable projector screen

Bower Fuller to introduce additional containment to access roof void in smaller roof void in Bean refurb adjacent velux, beyond hatch location

 Bean refurb roof awaiting tiling

Site debris on most scaffold areas- to be cleared- Action HCL

 Ponding to gutter area to main Bean LRC roof. HCL to advise

 Ditto

Ditto

 Ditto

 Velux modular rooflight installed

 Metsec requires addional profile to extend to 200mm so internal walls flush as CVA comments

 Stud partition Cunliffe GFL CU.00.16- set out out of plumb. CONDEMNED. Hutton to rebuild

Cunliffe hit and miss brickwork vent panel constructed without solids as specified. Also opening not yet formed internally therefore built out of correct sequence. CONDEMNED.To be rebuilt- Action HCL

 Ditto- to be rebuilt in solids as specification and details. Soft joint correct.CONDEMNED. To be rebuilt- Action HCL

 GL 4/A 1FL- replace 2 No. stretchers damaged- To be rebuilt- Action HCL

Cunliffe GFL GL G/1- brickshield low level not yet completed and soon inaccessible- HCL to ensure brick slips and insulation go below profile also in this area- Action HCL

 RWP pipework- HCL to ensure coordination where rwp outlet locations altered and additional bends added- Action HCL
Scabbling still has not been carried out to concrete  reveal to BE.EW.01.04 despite assurances that this would be carried out BEFORE brickwork commenced at first floor level (refer email correspondence). Former now in place. Concrete out of required tolerances as Engineers specification. CONDEMNED- Action HCL.

 Ditto. CONDEMNED- Action HCL

  Ditto. CONDEMNED- Action HCL

 Air tight ceiling lining underway to Bean LRC 1FL. However building is not watertight and new linings are already wet. CONDEMNED. remove and make watertight before rebuilding.- Action HCL

 Ditto. CONDEMNED.- Action HCL

 1FL Bean LRC not watertight. Rooflights incomplete and unfinished. Works out of sequence.

 Drylining to Cunliffe Mechanical riser 1. Diamond drilling of slab carried out after drylining. All boards damaged. CONDEMNED. remove and replace.- Action HCL
  Rubble to many areas on site. Site to be cleared and tidied. Note dampness to plasterboards. CONDEMNED. remove and replace.- Action HCL

 1FL Cunliffe- classroom CU.01.07. Water ingress still apparent.

Water ingress to GFL plant area. This area must be watertight, clear and secure before any mechanical or electrical installations commence.