Site visit 13.08.15

Cunliffe brick remedials to complete

Bean Hall- vales to review acoustic panel re AV screen size/ location

Bean Hall- ply panels damaged- replace

Ditto

Ditto- water supply not required to face of servery- replace panel

Ditto rub out marks or replace

Ditto

Damage to ply panels to servery- replace

BE.EX.ED.00.01- remove ALL ironmongery before decorating and replace ALL ironmongery/ rehang door
Old Bean GFL under link- make good brickwork adjacent paving- out of sequence

Cunliffe under link- complete brickshield before landscape- out of sequence

HCL to advise matwell frame BE.ED.00.06- steps out from wall- infill material or adjust? Advise

Ditto adjacent stair- HCL to advise

Lockers/ opening formed mismatched- packing or infill required- HCL to advise

1st floor Bean corridor leading to reading room- in progress

BE.ID.01.03- brick treatment/ cut required but oak frame already installed- out of sequence works- HCL to advise/ protect to complete

Bean stair refurb- HCL to advise on brick doctor/ aluminium pressing to corners

Seminar stair- work required to slurry wall/ perimeter to 1st floor fire rated windows- Action HCL

Seminar stair rooflight opening nearing completion- awaiting sailblind

Attenuating cowls sitting too high above roof finish- radius to fitting does not accommodate build up of lead over duct- HCL to remake lower section of cowls and refit
 Ditto- otherwise visible in elevation. No sample or drawing issued or approved by design team. HCL to address problem.

TEK vent fitted but drawings not finalised and comments not accommodated. Unit projects beyond face of brick as CVA comments- must be set back and continual weathering added over. Also not metal profile fitted to brickshield. Complete and refit as comments- Action HCL

Ditto brickshield reveal- not as CVA specification- Rebuild as required- Action HCL- raised previously

Ditto TEK vent- internal finishes to be addressed also- Action HCL

Acoustic panels not fitted and CVA setting out issued- Rehang- Action HCL

1st bay to arcade- 2 No. bolts projecting/ brick to be made good/ staple removed- Action HCL

Ditto- remove staining to brickwork- Action HCL

Bean Hall- induction loop being fitted- HCL to ensure protected until carpet fitted- Action HCL

Bean refurb steelwork- decorations in progress

Bean 1FL- emergency exit sign should be centralised over brick opening as CVA setting out- Action HCL

Downpipe to be added externally 1 FL triangle roof- Action HCL

Oak to match adjacent to vaulting 1FL Bean refurb- Action HCL

Cunliffe stair- panelling underway

CU.ID.00.15- carpet/ tiling interface not level- HCL to address

Oak linings underway to Bean 1FL- Action HCL

Thursday, 6 August 2015

Site visit 05.08.15

 Bean 1FL- recess to be extended as CVA DWG BE 07.1- current clash with blind installation

 Cunliffe 1FL CU 01.01- walls made good- awaiting decs.

 Cover detail Cunliffe West Stair- wide skirting detail to continue to external wall as agreed on site- to account for skewed stair geometry

 Cunliffe/ Bean interface- low level brickshield still incomplete and inaccessible as earlier CVA comments- HCL to advise

 Cunliffe East Stair 2FL- discrepancy from HRW detail as previously raised- HCL to provide detail as built and confirm compliance/ calcs for guarding requirements- Action HCL

Ditto

 Bean LRC overview

 Bean West Elevation GFL- Movement joint not full depth/ cut into brickwork. HCL to address- Action HCL
 Paving underway West Elevation Bean LRC

 Cunliffe 1FL walls/ ceiling interface to refurb- junction poor- HCL to address bead/ seal- Action HCL

 Bean LRC stair landing 1FL- conflict with Bower Fuller introduced bulkhead/ blind installation- HCL to address- Action HCL

 Bespoke joinery to link being used as contractors tool store/ unprotected and now damaged- HCL to advise on replacement/ remedial works where affected- Action HCL

 Cunliffe north elevation- awaiting completion of hit and miss vent panels

 Cunliffe- radiussed brickwork to bin sotre underway

 Pier to bin store- brickshield to Cunliffe still incomplete low level

Ditto- HCL to advise how brickshield will be completed where kerbs already installed- works out of sequence- Action HCL

 Cunliffe East elev- brickwork observation log now issued for completion- also remedials still to be completed- Action HCL

 Slurry mix applied to seminar stair wall- trim to fire-rated windows discussed. CVA to review with Jansen/ HCL to investigate powder coated profile as opening uneven- Action CVA/ HCL

 Bean refurb GFL- walls to be made good- Action HCL

 Mastic applied to link- awaiting trims/ cappings/ flashings

 Remedial works carried out to Cunliffe 1FL window heads but no proposal forwarded to CVA/ HRW for comment. HCL to forward for comment- Action HCL

 Bean stair refurb- HCL to investigate making good/ replacement of bricks as specified- alternatively aluminium PPC self coloured pressing- HCL to advise

 Render to old bean underway - bead position not as per CVA sketch.

 Paving detail- HCL to ensure gap consistent to perimeter

Paving underway West elevation Bean LRC
 