Cunliffe 1FL CU 01.01- walls made good- awaiting decs.
Cover detail Cunliffe West Stair- wide skirting detail to continue to external wall as agreed on site- to account for skewed stair geometry
Cunliffe/ Bean interface- low level brickshield still incomplete and inaccessible as earlier CVA comments- HCL to advise
Cunliffe East Stair 2FL- discrepancy from HRW detail as previously raised- HCL to provide detail as built and confirm compliance/ calcs for guarding requirements- Action HCL
Ditto
Bean West Elevation GFL- Movement joint not full depth/ cut into brickwork. HCL to address- Action HCL
Paving underway West Elevation Bean LRC
Cunliffe 1FL walls/ ceiling interface to refurb- junction poor- HCL to address bead/ seal- Action HCL
Bean LRC stair landing 1FL- conflict with Bower Fuller introduced bulkhead/ blind installation- HCL to address- Action HCL
Bespoke joinery to link being used as contractors tool store/ unprotected and now damaged- HCL to advise on replacement/ remedial works where affected- Action HCL
Cunliffe north elevation- awaiting completion of hit and miss vent panels
Cunliffe- radiussed brickwork to bin sotre underway
Pier to bin store- brickshield to Cunliffe still incomplete low level
Ditto- HCL to advise how brickshield will be completed where kerbs already installed- works out of sequence- Action HCL
Cunliffe East elev- brickwork observation log now issued for completion- also remedials still to be completed- Action HCL
Slurry mix applied to seminar stair wall- trim to fire-rated windows discussed. CVA to review with Jansen/ HCL to investigate powder coated profile as opening uneven- Action CVA/ HCL
Bean refurb GFL- walls to be made good- Action HCL
Mastic applied to link- awaiting trims/ cappings/ flashings
Remedial works carried out to Cunliffe 1FL window heads but no proposal forwarded to CVA/ HRW for comment. HCL to forward for comment- Action HCL
Bean stair refurb- HCL to investigate making good/ replacement of bricks as specified- alternatively aluminium PPC self coloured pressing- HCL to advise
Render to old bean underway - bead position not as per CVA sketch.
Paving detail- HCL to ensure gap consistent to perimeter
Paving underway West elevation Bean LRC
Seminar stair ceiling- filling of holes/ making good required prior to decoration