Thursday, 28 May 2015

Site visit 27.05.15

 2FL Cunliffe- arrow to escape sign to be changed to point left- Action HCL

  2FL Cunliffe- Window seat building out underway

  2FL Cunliffe- call point to be facing out adjacent door frame- Action HCL

  2FL Cunliffe-Steelwork to stair. CVA awaiting revised steel drawings following comments sent 01.04.15- status C. HCL to address discrepancies on site as raised in those comments- Action HCL

 1st FL Cunliffe CU.01.18 make good wall high level. Mastic between all preast floor elements- - Action HCL
 1st FL Cunliffe- mould to classrooms CU.01.01, 02, 03, 07 (severe) HCL to address moisture and fungal growth following inadequate protection of building fabric during construction- as raised on previous occasions. Action HCL

 Ditto
 Ditto behind Dado trunking

Ditto high level
Ditto  wall return

Door lining BE.ID.01.02, 03 incorrect- not as detail on 0331 BE 34.12. HCL to address

All redundant cabling to be removed as stated in contract documents- Action HCL

HCL raised discrepancy in floor level between old bean and new (variation in level of existing Bean) HCL to compensate with shallow ramp to entry- Action HCL

HCL to still provide details of high level ductwork where redirected away from gulley location to roof

Awaiting screed to stair landings in Cunliffe
HCL to make good soffit where opening up required for cabling

Tiling set out not as sketch- HCL to advise

Cunliffe  GFL to cleaners cupboard- gulley raised to correct level

Bean bride link awaiting glass installation

Awaiting cubicles to Bean LRC toilets

downpipe connection GL A/1 sits too low and will conflict with soffit panelling- not as CVA/ HRW details- HCL to address
Ditto GL A/2 and also ditto GL D/1

Remedial concrete works still to be carried out to precast lower beam and columns prior to decoration

Bean 1FL lightwell awaiting linings. Secondary steelwork installed to hang light fitting

CVA to review cubicle size/ rad position with building control

Mounting block and monument relocation underway

Cunliffe overview

AV cables now installed as of 21/05/15. Awaiting construction of secondary ceilings/ framework

Arcade lightwell construction underway

Ditto


Tuesday, 19 May 2015

Site Visit 15.05.15

 Arcade steel installed- timber infill underway

 Arcade/ Cunliffe interface. Hit and miss to be rebuilt following installation of ties/ cavity tray

 Arcade roof timbers/ deck underway

 Bean LRC overview

 Arch formers in process of being removed to arcade

 RWP penetrating through wall G/L A too low- panelling to arcade soffit cannot accommodate. HCL to reset higher- Action HCL

 Large format tiling installation underway to GFL Bean Hall

 Ditto. HCL to address DPC/ arch window upstand.

 Wash troughs now protected- tiling/ tile skirting underway to Bean LRC toilets

 HCL to provide altered setting out of lighting to seminar stair

 Insulation to be added to lightwell GL 2/A Bean

 Insulation added to Reception lightwell 1FL Bean

 Arch linings to be adjusted to GL A + D to ensure mirrored about 45 degrees from gridlines A/1 and D/1

 Arch linings 1st floor Bean LRC

 Rooflight carpentry to arcade built too high and not to CVA or Alucraft detail. CVA comments issued via Alucraft drawings. HCL to address on site

 Arcade rooflight carpentry underway

 Bean linings discussed. Additional profile may be required above fire-rated glazing. Refer CVA notes on HCL COI.

 4 Bay steelwork to new Cunliffe stair underway but drawings not status A. HCL to forward to CVA for further comment/ review- Action HCL

 Ditto

 Alucraft/ TEK drawings still awaited for Cunliffe 2FL window

 Cunliffe 2FL brickshield still to be carried out

 Cunliffe 2FL ceilings- perforated board installation underway. No quilt installed- Vales to added as specification K10/ 401D

 Cunliffe CU.02.02 window airtight head detail not as CVA detail

CU.02.02  Mechanical works in place awaiting kitchen

 Lighting installed to  2FL classrooms

 Bench seat to be formed over RWP as per 0331 4.2. Removable panel required to front face and access required due to change in direction. Action HCL

 Temp protection of light fittings- window linings trim still to be carried out

 Bulkhead to Cunliffe CU.01.02 to be tapered to end to avoid clash with window lining.

HCL to confirm bead/ mastic joint to fire-rated clerestory light GFL Cunliffe CU.00.03

 Library square overview

Lambs bricks on site for remedial works to Old Bean arch. HCL still to provide final drawings as requested by CVA- Action HCL

 HCL to advise regarding strap detail to fire rated glazing Bean LRC- not as CVA detail to upper storeys (GFL shown)

Tiling/ grouting underway GFL Bean LRC