 Arcade steel installed- timber infill underway

 Arcade/ Cunliffe interface. Hit and miss to be rebuilt following installation of ties/ cavity tray

 Arcade roof timbers/ deck underway

 Bean LRC overview

 Arch formers in process of being removed to arcade

 RWP penetrating through wall G/L A too low- panelling to arcade soffit cannot accommodate. HCL to reset higher- Action HCL

 Large format tiling installation underway to GFL Bean Hall

 Ditto. HCL to address DPC/ arch window upstand.

 Wash troughs now protected- tiling/ tile skirting underway to Bean LRC toilets

 HCL to provide altered setting out of lighting to seminar stair

 Insulation to be added to lightwell GL 2/A Bean

 Insulation added to Reception lightwell 1FL Bean

 Arch linings to be adjusted to GL A + D to ensure mirrored about 45 degrees from gridlines A/1 and D/1

 Arch linings 1st floor Bean LRC

 Rooflight carpentry to arcade built too high and not to CVA or Alucraft detail. CVA comments issued via Alucraft drawings. HCL to address on site

 Arcade rooflight carpentry underway

 Bean linings discussed. Additional profile may be required above fire-rated glazing. Refer CVA notes on HCL COI.

 4 Bay steelwork to new Cunliffe stair underway but drawings not status A. HCL to forward to CVA for further comment/ review- Action HCL

 Ditto

 Alucraft/ TEK drawings still awaited for Cunliffe 2FL window

 Cunliffe 2FL brickshield still to be carried out

 Cunliffe 2FL ceilings- perforated board installation underway. No quilt installed- Vales to added as specification K10/ 401D

 Cunliffe CU.02.02 window airtight head detail not as CVA detail

CU.02.02  Mechanical works in place awaiting kitchen

 Lighting installed to  2FL classrooms

 Bench seat to be formed over RWP as per 0331 4.2. Removable panel required to front face and access required due to change in direction. Action HCL

 Temp protection of light fittings- window linings trim still to be carried out

 Bulkhead to Cunliffe CU.01.02 to be tapered to end to avoid clash with window lining.

HCL to confirm bead/ mastic joint to fire-rated clerestory light GFL Cunliffe CU.00.03

 Library square overview

Lambs bricks on site for remedial works to Old Bean arch. HCL still to provide final drawings as requested by CVA- Action HCL

 HCL to advise regarding strap detail to fire rated glazing Bean LRC- not as CVA detail to upper storeys (GFL shown)

Tiling/ grouting underway GFL Bean LRC