Arcade/ Cunliffe interface. Hit and miss to be rebuilt following installation of ties/ cavity tray
Arcade roof timbers/ deck underway
Bean LRC overview
Arch formers in process of being removed to arcade
RWP penetrating through wall G/L A too low- panelling to arcade soffit cannot accommodate. HCL to reset higher- Action HCL
Large format tiling installation underway to GFL Bean Hall
Ditto. HCL to address DPC/ arch window upstand.
Wash troughs now protected- tiling/ tile skirting underway to Bean LRC toilets
HCL to provide altered setting out of lighting to seminar stair
Insulation to be added to lightwell GL 2/A Bean
Insulation added to Reception lightwell 1FL Bean
Arch linings to be adjusted to GL A + D to ensure mirrored about 45 degrees from gridlines A/1 and D/1
Arch linings 1st floor Bean LRC
Rooflight carpentry to arcade built too high and not to CVA or Alucraft detail. CVA comments issued via Alucraft drawings. HCL to address on site
Arcade rooflight carpentry underway
Bean linings discussed. Additional profile may be required above fire-rated glazing. Refer CVA notes on HCL COI.
4 Bay steelwork to new Cunliffe stair underway but drawings not status A. HCL to forward to CVA for further comment/ review- Action HCL
Ditto
Alucraft/ TEK drawings still awaited for Cunliffe 2FL window
Cunliffe 2FL brickshield still to be carried out
Cunliffe 2FL ceilings- perforated board installation underway. No quilt installed- Vales to added as specification K10/ 401D
Cunliffe CU.02.02 window airtight head detail not as CVA detail
CU.02.02 Mechanical works in place awaiting kitchen
Lighting installed to 2FL classrooms
Bench seat to be formed over RWP as per 0331 4.2. Removable panel required to front face and access required due to change in direction. Action HCL
Temp protection of light fittings- window linings trim still to be carried out
Bulkhead to Cunliffe CU.01.02 to be tapered to end to avoid clash with window lining.
HCL to confirm bead/ mastic joint to fire-rated clerestory light GFL Cunliffe CU.00.03
Library square overview
Lambs bricks on site for remedial works to Old Bean arch. HCL still to provide final drawings as requested by CVA- Action HCL
Tiling/ grouting underway GFL Bean LRC