Site visit 27.05.15

 2FL Cunliffe- arrow to escape sign to be changed to point left- Action HCL

  2FL Cunliffe- Window seat building out underway

  2FL Cunliffe- call point to be facing out adjacent door frame- Action HCL

  2FL Cunliffe-Steelwork to stair. CVA awaiting revised steel drawings following comments sent 01.04.15- status C. HCL to address discrepancies on site as raised in those comments- Action HCL

 1st FL Cunliffe CU.01.18 make good wall high level. Mastic between all preast floor elements- - Action HCL
 1st FL Cunliffe- mould to classrooms CU.01.01, 02, 03, 07 (severe) HCL to address moisture and fungal growth following inadequate protection of building fabric during construction- as raised on previous occasions. Action HCL

 Ditto
 Ditto behind Dado trunking

Ditto high level
Ditto  wall return

Door lining BE.ID.01.02, 03 incorrect- not as detail on 0331 BE 34.12. HCL to address

All redundant cabling to be removed as stated in contract documents- Action HCL

HCL raised discrepancy in floor level between old bean and new (variation in level of existing Bean) HCL to compensate with shallow ramp to entry- Action HCL

HCL to still provide details of high level ductwork where redirected away from gulley location to roof

Awaiting screed to stair landings in Cunliffe
HCL to make good soffit where opening up required for cabling

Tiling set out not as sketch- HCL to advise

Cunliffe  GFL to cleaners cupboard- gulley raised to correct level

Bean bride link awaiting glass installation

Awaiting cubicles to Bean LRC toilets

downpipe connection GL A/1 sits too low and will conflict with soffit panelling- not as CVA/ HRW details- HCL to address
Ditto GL A/2 and also ditto GL D/1

Remedial concrete works still to be carried out to precast lower beam and columns prior to decoration

Bean 1FL lightwell awaiting linings. Secondary steelwork installed to hang light fitting

CVA to review cubicle size/ rad position with building control

Mounting block and monument relocation underway

Cunliffe overview

AV cables now installed as of 21/05/15. Awaiting construction of secondary ceilings/ framework

Arcade lightwell construction underway

Ditto