Site visit 23.09.14

Plaster possibly to be removed in total to ICT office

Existing slab still protruding and visible high level to ICT classroom GFL. However within bulkhead so not visible after replastering

Cunliffe GFL survey still required following removal of existing floor finishes

Brickshield installation underway

Bean LRC west elevation overview

Brickshield installation problematic. Profile extends beyond installation

Gap cannot be made up with adhesive

Arcade north elevation.

HCL to ensure full mortar fill to all columns

Awaiting 2nd leaf construction to arches



Monday, 22 September 2014

Site visit 19.09.14

 Arch construction to Northern elevation of arcade underway

 Ditto
 Ditto- single skin- second skin to ensure full mortar fill

 Interface of brickwork and arch- longer brick to be cut in to eliminate large gap/ mortar joint


 
 Arcade brickwork internal view

 Carpentry underway to Bean 1FL roof

 Ditto

 RL.02.08- HCL to check orientation/ setting out (valley side)

 Cunliffe 2FL

Ditto

 Bean roof- stub steel to be cut prior to roof deck installation

 Link roof

 Cunliffe south elevation progress

 Cunliffe West Elevation brickwork support GFL level

 Cunliffe roof progress North elevation- rooflight installation underway

 CVA to review Alucraft sizes/ comments to link glazing. Possible setting out issue due to size of VE profile

 Ditto

Steelwork made good where previously drilled in error. Bean refurb GFL

 CVA to review perimeter dado tiling options and discuss with client/ obtain pricing for options

Relief arch- packers removed. Awaiting pointing/ additional brick skin infill to form door opening

Thursday, 4 September 2014

Site visit 02.09.14

Brickwork underway to arch arcade north elevation

Arch to arcade corner G/L D

Arch detail G/L C and north elevation

Discrepancy to concrete bearing for steelwork G/L A/2-3 1FL closed store

Ditto
 
Issue with plate of steel bearing onto lift shaft 1FL

CVA to review interface between glazed link and interface with existing Bean 1FL

Packing required to steelwork GL 2/D 1FL

Triangular opening/ general reading room 1FL Bean

Ditto

Overview of Bean with arch formers in situ for arcade

Cunliffe remedial steelwork now installed 1FL

Cunliffe roof- carpentry/ insulation underway

Rooflight setting out to be reviewed for CU.RL.02.08. HCL to confirm as setting out issued

Cunliffe south elevation overview


Bean stair now succesfully positioned

Ditto