Arch construction to Northern elevation of arcade underway
Ditto
Ditto- single skin- second skin to ensure full mortar fill
Interface of brickwork and arch- longer brick to be cut in to eliminate large gap/ mortar joint
Arcade brickwork internal view
Carpentry underway to Bean 1FL roof
Ditto
RL.02.08- HCL to check orientation/ setting out (valley side)
Cunliffe 2FL
Ditto
Bean roof- stub steel to be cut prior to roof deck installation
Link roof
Cunliffe south elevation progress
Cunliffe West Elevation brickwork support GFL level
Cunliffe roof progress North elevation- rooflight installation underway
CVA to review Alucraft sizes/ comments to link glazing. Possible setting out issue due to size of VE profile
Ditto
Steelwork made good where previously drilled in error. Bean refurb GFL
CVA to review perimeter dado tiling options and discuss with client/ obtain pricing for options
Relief arch- packers removed. Awaiting pointing/ additional brick skin infill to form door opening