Preparing for pouring of slab to Cunliffe
Bean LRC
Ditto
Reinforcement to Cunliffe slab underway
Lift pit complete
Threshold to lift cast GFL- with recess for door
Kickers complete to Bean LRC
Pipes to be protected to below ground drainage
Preparations for below ground drainage to Cunliffe
Ditto
Tuesday, 28 January 2014
Thursday, 16 January 2014
Site Visit 15.01.14
Reinforcement to Bean slab. Awaiting collapsible board substructure formwork
Ditto
Majority of Bean LRC slab now cast
Existing floor surfaces/ levels. RW to survey and forward info for review
Cuts made in preparation fo service routes through existing slab
Cunliffe wall- plaster to be removed in lieu of Ibstock brickshield insulation.
Clerestory light removed in lieu of further demolition
Starter bars for concrete walls to Bean LRC
Screed to 2FL- levelling will be required once partitions/ walls/ roof removed- HCL/ CVA to liaise regarding levels once roof removed
Bean LRC slab from 2FL Cunliffe
Cunliffe with brick infills
Cracking around reinforcement in 2 No. Locations- HRW to comment
RWP pipe to corner of Bean/ Arcade
Ditto
Majority of Bean LRC slab now cast
Existing floor surfaces/ levels. RW to survey and forward info for review
Cuts made in preparation fo service routes through existing slab
Cunliffe wall- plaster to be removed in lieu of Ibstock brickshield insulation.
Clerestory light removed in lieu of further demolition
Starter bars for concrete walls to Bean LRC
Screed to 2FL- levelling will be required once partitions/ walls/ roof removed- HCL/ CVA to liaise regarding levels once roof removed
Bean LRC slab from 2FL Cunliffe
Cunliffe with brick infills
Cracking around reinforcement in 2 No. Locations- HRW to comment
RWP pipe to corner of Bean/ Arcade
Thursday, 2 January 2014
Site Visit 20.12.13
Formwork for slab edge to Bean underway
Ditto
Blinding/ Hardcore under slab to Bean
Cunliffe following stair removal
Bean LRC lift pit formwork underway
1FL Cunliffe
1FL Cunliffe- window openings temporarily covered
Bean LRC blinding/ hardcore prior to slab pour
Duct to stage
Steel to 1FL Cunliffe. Cover meter survey to be carried out to slab. Removal/ replacement of steel options to be developed by HRW
Conflict with existing steel and proposed opening underneath- to be aligned with adjacent opening
Manhole to arcade
Cunliffe rear elevation post- soft strip
Bean side elevation post-soft strip
Hardcore/ blinding in preparation for slab
Formwork preparation for lift shaft
Ditto
Blinding/ Hardcore under slab to Bean
Cunliffe following stair removal
Bean LRC lift pit formwork underway
1FL Cunliffe
1FL Cunliffe- window openings temporarily covered
Bean LRC blinding/ hardcore prior to slab pour
Duct to stage
Steel to 1FL Cunliffe. Cover meter survey to be carried out to slab. Removal/ replacement of steel options to be developed by HRW
Conflict with existing steel and proposed opening underneath- to be aligned with adjacent opening
Manhole to arcade
Cunliffe rear elevation post- soft strip
Bean side elevation post-soft strip
Hardcore/ blinding in preparation for slab
Formwork preparation for lift shaft
Subscribe to:
Comments (Atom)




























