Tuesday, 28 January 2014

Site Visit 24.01.14

 Preparing for pouring of slab to Cunliffe

 Bean LRC

 Ditto

 Reinforcement to Cunliffe slab underway

 Lift pit complete

 Threshold to lift cast GFL- with recess for door

 Kickers complete to Bean LRC

 Pipes to be protected to below ground drainage

 Preparations for below ground drainage to Cunliffe

Ditto

Thursday, 16 January 2014

Site Visit 15.01.14

 Reinforcement to Bean slab. Awaiting collapsible board substructure formwork

 Ditto

Majority of Bean LRC slab now cast

 Existing floor surfaces/ levels. RW to survey and forward info for review

 Cuts made in preparation fo service routes through existing slab

 Cunliffe wall- plaster to be removed in lieu of Ibstock brickshield insulation.

 Clerestory light removed in lieu of further demolition

Starter bars for concrete walls to Bean LRC

Screed to 2FL- levelling will be required once partitions/ walls/ roof removed- HCL/ CVA to liaise regarding levels once roof removed

Bean LRC slab from 2FL Cunliffe

 Cunliffe with brick infills

 Cracking around reinforcement in 2 No. Locations- HRW to comment

RWP pipe to corner of Bean/ Arcade

Thursday, 2 January 2014

Site Visit 20.12.13

 Formwork for slab edge to Bean underway

 Ditto

 Blinding/ Hardcore under slab to Bean

 Cunliffe following stair removal

 Bean LRC lift pit formwork underway

1FL Cunliffe
 1FL Cunliffe- window openings temporarily covered

 Bean LRC blinding/ hardcore prior to slab pour

 Duct to stage

 Steel to 1FL Cunliffe. Cover meter survey to be carried out to slab. Removal/ replacement of steel options to be developed by HRW

 Conflict with existing steel and proposed opening underneath- to be aligned with adjacent opening

 Manhole to arcade

 Cunliffe rear elevation post- soft strip

 Bean side elevation post-soft strip

 Hardcore/ blinding in preparation for slab

Formwork preparation for lift shaft