Preparing remainder of site compound
Gable end to rear of Bean now removed
Client bin store concrete base now complete and outside of compound.
Bean demolition of gable element complete.
Corbelled element to be reviewed where forming seminar stair area.
Making good/ forming of new opening to be reviewed
Arch/ opening/ relief to be reviewed against proposals
Ditto
Cunliffe gable end under demolition
Ditto
Opening between Bean & Cunliffe
Bean side elevation
Bean GFL interior. Tile dado to perimeter to be made good
New timber profile/ bead to be considered to perimeter- existing panelling etc. to be removed
1FL Bean- shelving removed where new openings to be formed
Ditto
Monday, 28 October 2013
Thursday, 17 October 2013
Site Visit 17.10.13
Existing openings revealed following demolition of single storey elements
Ditto. CVA to review in relation to existing drawings
Ditto. CVA to review in relation to existing drawings
Ditto. CVA to review in relation to existing drawings
Ditto. CVA to review in relation to existing drawings
Ditto. CVA to review in relation to existing drawings
Ditto. CVA to review in relation to existing drawings
Tuesday, 15 October 2013
Site Visit 14.10.13
Temporary road construction underway
existing cables removed from buildings in lieu of proposed demolition of gable/ single storey extensions
Cunliffe Stair element awaiting demolition
AV units have been degassed- awaiting removal
Anticipated damage to arch now fully evident following removal of glazed canopy/ roof
Canopy removed
Urinals/ wcs awaiting removal
Paintings to be removed- CVA to liaise with school
Walls removed to Cunliffe
Site compound overview
Ditto
Tile damage following removal of furniture by school. Dado/ cover detail may be required
Bean 1FL internal
Cunliffe- demolition in progress
Cunliffe- canopy to be removed
1FL slab- additional making good will be required
Ditto
Services diversions discussed- additional notes to follow
Manhole adjacent Main School- additional notes to follow
existing cables removed from buildings in lieu of proposed demolition of gable/ single storey extensions
Cunliffe Stair element awaiting demolition
AV units have been degassed- awaiting removal
Anticipated damage to arch now fully evident following removal of glazed canopy/ roof
Canopy removed
Urinals/ wcs awaiting removal
Paintings to be removed- CVA to liaise with school
Walls removed to Cunliffe
Site compound overview
Ditto
Tile damage following removal of furniture by school. Dado/ cover detail may be required
Bean 1FL internal
Cunliffe- demolition in progress
Cunliffe- canopy to be removed
1FL slab- additional making good will be required
Ditto
Services diversions discussed- additional notes to follow
Manhole adjacent Main School- additional notes to follow