Preparing remainder of site compound
Gable end to rear of Bean now removed
Client bin store concrete base now complete and outside of compound.
Bean demolition of gable element complete.
Corbelled element to be reviewed where forming seminar stair area.
Making good/ forming of new opening to be reviewed
Arch/ opening/ relief to be reviewed against proposals
Ditto
Cunliffe gable end under demolition
Ditto
Opening between Bean & Cunliffe
Bean side elevation
Bean GFL interior. Tile dado to perimeter to be made good
New timber profile/ bead to be considered to perimeter- existing panelling etc. to be removed
1FL Bean- shelving removed where new openings to be formed
Ditto