Thursday, 30 July 2015

Site visit 29.07.15

CU.ED.00.08- additional hatch required for transformer to external bricklight

CU.ED.00.04- ditto

HCL still to construct solid balustrade to 1FL half landing. If not steel frame to HCL details then HCL to forward details for comment- Action HCL

CU.ID.02.16 door catching on tiles- now marked. Tile to be replaced, door raised to suitable height- Action HCL
Cunliffe coping GL G- poor pointing/ flashing. Rebed- Action HCL
Cunliffe coping GL A-B. Not as CVA detail. Specials not used as CVA/ Ibstock details. Remove and replace as CVA details. Action HCL

Ditto

HCL to confirm cill detail to CU.EW.02.11 as not as original CVA detail. Action HCL

Reveal detail not as CVA details. To be replaced. Action HCL

Bean LRC repairs still underway. All clips, cables etc. to be removed as CVA details.Action HCL

Ditto

Awnings installation underway to Cunliffe. Pressed metal head flashing still to be completed.- Action HCL

Brickshield to Cunliffe- GL A-B/ 1- brickshield poorly applied- finish and pointing inconsistent- remove and reapply- Action HCL
Damage adjacent RWP 2FL- remove damaged slips and reapply/ repoint- Action HCL

Tiles to roof still not mixed as per spec. - HCL to address- Action HCL

No soft joints to Brickshield as per CVA details CU 30.2, CU 30.3. Joints to be raked out and movement joint added as per drawings and specification. Action HCL

Perforate lining to Bean RL.01.01. Plasterboard misaligned RHS photo low level triangular reveal. Hole filling inconsistent with details. HCL to address- Action HCL

Ditto RL.01.03
 
Cunliffe 2FL riser- air tightness to be addressed where gaps- Action HCL

Hard landscape underway adjacent Ashton building

Site visit 24.07.15

 Framing underway to Bean link soffit trespa cladding

 CVA to check spec. for Cunliffe tiling adjacent water fountains as inconsistencies on site- 2FL + 1FL-POSTSCRIPT- 1st floor tiling to CU.01.05 wc lobby area incorret. Finish should be natural not Bocciardato- Action HCL
 Trespa lining underway to arcade. HCL to clean all panels on completion- Action HCL

BE.00.14- acoustic panel hanging- ceilings to all be made good where damage to soffit on installation- Action HCL
 BE.00.14 bulkhead- incorrect ceiling not removed and 2 further ceilings added- not as CVA detail BE 12.4
 Ceiling hatches to BE.00.14- problems with fitting due to location of tray above- HCL to advise

 BE.00.10 precast concrete column/ beam- to be made good/ redecorated as per previous comments regarding finish of concrete- Action HCL

 Bean stair BE.00.02- awaiting carpet/ nosings. New stair tile to corners as M10/ 116- HCL to advise

 Water ingress to  BE.EW.01.06. Screen awaiting capping. Plasterboard now damaged. Replace and make good decorations- Action HCL

 Ditto- water ingress to be addressed

 Sedum now installed to arcade roof

BE.RL.01.01- Interface to rooflight lantern linings- holes filled poorly/ inconsistent. HCL to address - Action HCL

 BE.RL.01.04- perforate plasterboard to ends- boards do not align/ edge bead required- Action HCL

  
Ditto

 BE.RL.01.01-lining not as CVA detail BE 12.5- lining to align vertically with window board and not extend to glazing. HCL to modify and set back nominal 50mm and apply edge bead to finish.- Action HCL


 BE.EW.01.08- lining completed internally but water ingress issue not addressed- DPC/ EDPM to be completed as CVA detail BE 15.3- Action HCL

 BE.EW.01.08- ceiling/ lining not completed as CVA detail BE 15.3- Action HCL

 New joinery stained/ damaged/ still unprotected- Action HCL
 Edge detail to MDF window reveals generally poor- HCL to make good surface/ decoration- Action HCL
 CU.ID.02.06- door catching/ marking tile

 Ditto MDF window reveals

 CU.ID.00.15- threshold/ level to be addressed- Action HCL

 Bean LRC overview

 Hit and miss brickwork above CU.ED.00.05 to be removed/ grille added/ support added/ brick rebuilt- Action HCL
 Bean 1FL interior overview

 RCP recess not as CVA detail BE 07.1- slot to be continuous. - Action HCL

Bean LRC link-ceiling airtight detail not as CVA details BE 18.2 or subsequent HCL sketch- Action HCL

Monday, 20 July 2015

Site visit 13.07.15

 Bean toilets GFL- infill required between window reveal and wall/ tiling

 Bean GFL BE.ED.00.04- no cavity closer/ insulation to cavity/ profile required to close gap between mullion and brickwork. Gap greater that Alucraft drawings as previously commented

 Background heating installed to 'shop window' display BE.EW.00.11

 Bean 1FL- perforated platerboard. Excessive filling to holes where planes interface. No edge beads to high level where interface with rooflight

 Arcade roof awaiting sedum installation and aluminium kerb completion

 Grille to Bean 1FL ceiling- clash with wall. CVA to provide additional grille to eliminate

 Additional stop bead required to reveal glasroc to arches-1FL Bean. Refer BE 12.3. -Action HCL

 Scaffold pole screeded-in and craked. Remedial works required- Bean 1FL link -Action HCL

 Make good internal wall/ dab on plasterboard- Cunliffe CU.01.08 -Action HCL

 Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL

 Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL

 Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL



  Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL

 Cunliffe 2FL riser adjacent CU.EW.02.07- ensure sealed/ airtight as previous comments/ SVR -Action HCL

 Mastic to north elev Cunliffe- downpipes- poor workmanship- joint not tooled correctly- HCL to address
Ditto

 Bean LRC overview

 Bean arcade soffit- framing underway

 Bean GFL hall- ply lining underway

 Ditto

 Ply lining damaged adjacent where matwells made good. HCL to address

 Additional hatch formed for services access Bean GFL

 Bean link joinery display case underway

 Arch ventilation grilles installed Bean 1FL

 BE.ID.01.05- door needs to be raised as catching on ply. Carpet still to be laid- Action HCL

 Clash at head of FCUJ.03 but panel removeable to allow hatch access.

 Remedial works required to back-to-back trough Cunliffe -Action HCL

 CU.00.15- ceiling requires attention around hatch where ill-fitting -Action HCL

 Remedial works required to window reveal CU.00.15 -Action HCL

 Brickshield East elev- still incomplete. -Action HCL

 Alarm to be lowered as will clash with trespa soffit/ insulation under link- Action HCL


 Hard landscape underway adjacent Ashton

Brickshield/ brickwork remedials- provisional observation log to be issued by CVA -Action HCL