Tuesday, 7 July 2015

Site Visit 06.07.15

 Arcade soffit framework complete- awaiting trespa paneling. Ply lining not as CVA detail- should be consistent and level at top. As alternative CVA will accept trespa lining to run upto underside of schuco rooflight mullion with approx 10mm consistent gap to perimeter- Action HCL

 Bean Hall sliding door BE.EW.00.03- pressed metail lining to be added to cover cavity closer. Timber to also be fixed securely over prior to pressed metal trim to head- Action HCL

 Drylining detail to refectory not as CVA detail BE 18.1.- refer Sec 7.

 Panelling not protected to Bean Hall. Adequate protection to be given especially where decorations and prep required over panelling- Action HCL

 Ditto protection
 Bean Hall joinery- Centre panel to be fixed and Keku either side to allow cabling/ access etc.- Action HCL
 BE.EW.00.06- cill detail not as CVA dwg BE 13.3. HCL to advise of alternative detail to finish- Action HCL

 Doors still unprotected 2FL Cunliffe

 Fire/ acoustic separation still required under Bean stair- Action HCL

 Arch linings- plasterboard/ skim underway. Slot to bulkhead to be continuous- HCL to correct- Action HCL
 Ditto

G/L 1/A 1FL- Detail where arches join to be equidistant- as raised at previous site visits. Current detail condemned- HCL to adjust- Action HCL

Ditto G/L 1/D

 Bower Fuller raised query about additional hatch required- CVA to review

 Bower Fuller request additional hatch to ceiling GFL Bean

Pigeon infestation to old Bean/ loft. Pigeons to be removed/ building secured as health & safety risk

Latex screed to Old Bean LRC GFL- poor workmanship, bricks incorporated? and levels unresolved- condemned

Ditto

Ditto

Ceiling bulkhead  to Old Bean GFL at wrong level and previously condemned has now been plastered. Level still incorrect and not as CVA detail Det 1,2 BE 12.4. Remains condemned- HCL to address- Action HCL

Ditto

Perimeter lining to Old Bean LRC GFL- flush skirting detail not carried out and condemned at earleir site visit. Still unchanged. Action HCL.


Screed removed to door threshold BE.ID.00.09. HCL to advise why.

Bauder prep in lieu of sedum to arcade roof

Archive display joinery installed to BE.EW.00.11

Arch repaired over  BE.EW.00.01

 Awaiting snag to all of Cunliffe brickwork. CVA to review next week. Chips to glazed brick at GFL require replacements- Action HCL

Landscape works underway between Bean & Ashton

MOT Type 1 on site- CVA to check w/ HRW if compliant with specification