Tuesday, 30 June 2015

Site visit 26.06.15

 Bean LRC 1st flr- Bulkhead to shadow recess incorrect GL 1/C- refer BE 7.1,

 Bean LRC 1st flr- as window has been set 1 brick too high there is now an issue with the grille and detail which deviate from CVA detail. Cill level to be 1m AFFL to ensure consistency with loose furniture. HCL to advise of revised grille size.
 Ditto
 Mould still very present 1FL Cunliffe- Action HCL

 Ditto

 Ditto

 Clash between curtain wall and capping detail- to be addressed alongside fitting of pressed metal capping detail/ when pressed metal flashings applied- Action HCL

 capping detail G/L 3/A- requires resin fill- also G/L 3/C. Flashings as H71 still to be applied. Action HCL


 Cunliffe 2fl window reveal CU.ED.02.01 brickshield incorrect. Whole cut bricks with solid return required to corners. mitred/ glued slips unacceptable- Action HCL 
Ditto

 Cunliffe steel balustrade 2FL- 4 Bay revised drawing still required showing proposed remedials. No drawing received since comments of 09.06.15. Steel infill undersized- Action HCL

 No temporary protection on any new doors or bespoke fitted joinery. Any damage will need to be made good/ items replaced- Action HCL

 Ditto

 Entire site strewn with rubbish making movement around site hazardous. Unacceptable- HCL to address- Action HCL
 Framing underway to underside of arcade- black neoprene spacer required as per standard trespa spec H20/ 155A
 Ditto

 Insulation required to underside of soffit- link

 Infill panels required above long precast beam to Bean Hall GFL. Coffers with ducts can be exempt as covered in perforated panelling. Fixing can be discussed/ sketched by CVA if required- Action HCL

 Bean LRC lobby bulkhead soffit to be removed and set at correct height- Action HCL

Marshalls office- screen removed in error. HCL to reconstruct and fit - Action HCL

 Detail of screen to match adjacent doors

 Making good of strair drylining required Bean LRC- Action HCL


  Ditto acoustic/ fire protection. Stringer/ skirting to stair to be consistent with arris- Action HCL


 Bean LRC perimeter ceiling detail 1FL- drylining around steel required locally within reveal- Action HCL



 Librarians office- plasterboard/ plaster incomplete behind dado- Action HCL
Ditto

 Ditto
 cill/ EDPM to be addressed BE.EW.01.08- Action HCL


 Plasterwork/ taping and jointing poor 1FL classrooms- Action HCL


Bean rooflights- airtightness detailing poor- Action HCL


Level of glazing to pyramid rooflights in relation to slate roof not as CVA details or Alucraft details C629-D112-4. HCL to advise

Airtightness details to be carried out internally prior to glazing- Action HCL


Awaiting grilles to plantroom enclosure. Upper level flashing to be addressed once installed- Action HCL


Trespa fitted to classroom block entry- no neoprene installed - Action HCL

Ditto- Action HCL