Discrepancy between skirting tile and wall panel- CVA to instruct wall tile to gap
Bean LRC GFL- awaiting screed/ latex infill
Monument- build up not stone but brick/ render
Bean LRC 1FL reading room- linings underway
Awaiting installation of rooflight windows
Awaiting acoustic plasterboard/ quilt to Bean 1FL lightwell
Water ingress to Bean window BE.ID.01.05- HCL to address
Ditto
First glazed screen to link installed- awaiting upper fritted spandrel panel. Handrail structure also to be fitted. HCL to forward details for CVA comments- Action HCL
Lining detail as BE 34.12 detail 1 jamb profile- Action HCL
lintols to BE.ID.01.02,03 set at incorrect height- refer detail on PR34.12- HCL to address
Arcade scaffold now removed- pointing of remaining arches underway
Ceiling level incorrect to Bean GFL bulkhead- to be flush with lower web of steelwork as CVA detail BE12.4- HCL to address
Bean stair tiling/ nosing tiles now corrected. Tiling complete but unprotected. HCL to address
Tiling set out from opposite wall (not centrally). Wall out of square. Adequate acoustic and fire protection required between stair and wall. Additionally skirting will not cover large deviations in construction- beyond all allowed tolerances. HCL to address all issues
Ditto- acoustic and fire separtion required. Works out of sequeance as walling and decorations still incomplete. Tiling unprotected. HCL to address all issues
Acoustic lining to be built out as detail BE 12.5. Airtight lining not sealed to rooflight frame. Airtight lining also out of tolerance with frame. HCL to address. Action HCL
Bean Hall GFL. Actuators fitted to fanlight windows incorrectly. No fused spur provision. CVA comments of 03.06.14 highlight this. HCL to advise
Brickwork high level 2FL unsupported. HCL advised to address immediately- Action HCL