Thursday, 4 December 2014

Site visit 03.12.14

 Cunliffe/ Bean refurb overview. Temporary roof being removed

 Bean LRC overview

 Arch GL/ A demolished- to be rebuilt at correct spring height. All reinforcement to be reinstated as originally specified. Action HCL

 Bricks cannot be salvaged- HCL confirm that 20000 No. additional bricks secured. All reinforcement to be reinstated as originally specified. Action HCL

 Stair BE.00.11. Bottom tread/ stair set too low. HCL to raise. Also screed not set for matwell recess as required. HCL to adjust

 Further adjustment required to screeds/ levels GFL BeanLRC / Bean refurb. Action HCL

 CVA to instruct minor area of render to be carefully removed adjacent BE.ED.00.04.

 Bean 1FL airtight ceilings. Mastic seal/ full board coverage required to form air tightness line. HCL to address throughout
Bean 1FL GL 1/A- air tightness detail not achieved to corner. Further boarding/ mastic required.  HCL to address throughout


Water damaged boards retained and overboarded- HCL to address. Action HCL

Brickwork to be adjusted to window opening reveal BE.EW.01.06

Ditto

Grout to be removed from facing brickwork adjacent BE.EW.01.04

Intermediate arches to be removed and rebuilt at correct spring point height.

Corner detail to arcade

Parapet to arcade

Services penetration builderswork close to glazing within link- CVA to check

Ditto

Intumescent paintwork to be carried out prior to services installation. HCL to advise of programme

Containment fitted to 1FL demi-deck soffits

Ditto

Infill masonry/ making good required to Cunliffe 2FL stairwell

Level changes/ screed issues to be reported on 2FL Cunliffe. Discrepancy between stair landing and required raised floor voids. Action HCL

Insulation to Cunliffe roof to be addressed. Loose panels still apparent. U value not achieved. Action HCL

Brick/ lintol added to openings in lieu of cement slurry mix BE.IW.01.02,3

4 No. courses of brickshield slips laid poorly. To be removed and relaid level. Action HCL

Ditto

Cable route to main school reviewed. CVA to liaise with OR regarding route confirmation- Action CVA/ OR

Bean roof refurb- CVA to instruct infill timber to eaves detail.


Gutter to be monitored with view to setting forward/ lower.


Tiles mismatch to north face Bean roof refurb. To be adjusted- Action HCL

CU.EW.01.16- head level to be confirmed- Action CVA.

Flashings to be completed- Bean refurb roof

Cunliffe brickwork south elevation- underway 1FL

Bean refurb. Brick repair samples. To be toned back/ reviewed with client

Ditto

Plasterboard water damaged before fitting GFL Cunliffe CU.00.10. To be replaced- Action HCL

Ditto

Ditto

CVA to confirm continuation of dado trunking to return wall to enable feed to external wall- CU.00.12. Action CVA

Friday, 28 November 2014

Site visit 26.11.14

 Arch formers to lawn stage. All formers to be removed and herras fence reinstated as site set-up drawing to avoid damage of built fabric

 Internal arcade arches incorrectly set-out. 3 No. to be rebuilt from spring-point.

 Stud partitions underway to GFL Bean LRC

 Tray installation commenced to Bean LRC Hall GFL

 Lift pit to be drained.

 Library cloak areas GFL Bean LRC

 1FL Bean LRC. Airtight ceiling plasterboard to be replaced where panels damaged by water ingress.
 M&E coordinator to forward drawing of overlay of 1200 grid of unistrut/ structural ties/ mechanical plant

 
 Ditto


 Velux modular rooflight installed

 Concrete infill proposals acceptable- HCL to carry out

 Brick/ block detail discussed with bricklayer. Cavity to be continuous

 Bean LRC 1FL overview

 Cunliffe CU.01.20 walls to stairwell to be lined- plasterboards to be dabbed on. grout to be chipped away carefully high level.

 Cunliffe 2FL insulation. All insulation to be secured, gaps taped etc. to ensure U values achieved, continuity achieved.

 Brickshield ongoing to Cunliffe GFL

CVA to review provision for fireproofing of steel and instruct accordingly

Setting out of radiators discussed with Bower Fuller. Disabled cubicles CU.00.10 and CU.01.13 incorrectly set out- space provision inadequate- Vales to adjust partitions accordingly to CVA setting out
Grout now added GL D 1FL Bean LRC where required.

Cunliffe Hit and miss now built in solids. Remedials still to be carried out where incorrect


1FL Cunliffe brickshield ongoing

Cunliffe South Elevation overview. Brickwork at mid 1FL level. HCL to ensure adequate ties added as specified

Bean Refurb roof. Gutter level/ projection to be confirmed following installation of insulation

Flashing to pitched dormer/ valley detail

Soaker installation complete- awaiting flashing

Bean LRC roof- Bauder/ outlet levels/ pooling to be addressed with lower level insulation around outlet.

Ditto

Green Bauder installation commenced. Rooflight covering/ slate etc. still to be completed.