Friday, 28 November 2014

Site visit 26.11.14

 Arch formers to lawn stage. All formers to be removed and herras fence reinstated as site set-up drawing to avoid damage of built fabric

 Internal arcade arches incorrectly set-out. 3 No. to be rebuilt from spring-point.

 Stud partitions underway to GFL Bean LRC

 Tray installation commenced to Bean LRC Hall GFL

 Lift pit to be drained.

 Library cloak areas GFL Bean LRC

 1FL Bean LRC. Airtight ceiling plasterboard to be replaced where panels damaged by water ingress.
 M&E coordinator to forward drawing of overlay of 1200 grid of unistrut/ structural ties/ mechanical plant

 
 Ditto


 Velux modular rooflight installed

 Concrete infill proposals acceptable- HCL to carry out

 Brick/ block detail discussed with bricklayer. Cavity to be continuous

 Bean LRC 1FL overview

 Cunliffe CU.01.20 walls to stairwell to be lined- plasterboards to be dabbed on. grout to be chipped away carefully high level.

 Cunliffe 2FL insulation. All insulation to be secured, gaps taped etc. to ensure U values achieved, continuity achieved.

 Brickshield ongoing to Cunliffe GFL

CVA to review provision for fireproofing of steel and instruct accordingly

Setting out of radiators discussed with Bower Fuller. Disabled cubicles CU.00.10 and CU.01.13 incorrectly set out- space provision inadequate- Vales to adjust partitions accordingly to CVA setting out
Grout now added GL D 1FL Bean LRC where required.

Cunliffe Hit and miss now built in solids. Remedials still to be carried out where incorrect


1FL Cunliffe brickshield ongoing

Cunliffe South Elevation overview. Brickwork at mid 1FL level. HCL to ensure adequate ties added as specified

Bean Refurb roof. Gutter level/ projection to be confirmed following installation of insulation

Flashing to pitched dormer/ valley detail

Soaker installation complete- awaiting flashing

Bean LRC roof- Bauder/ outlet levels/ pooling to be addressed with lower level insulation around outlet.

Ditto

Green Bauder installation commenced. Rooflight covering/ slate etc. still to be completed.

No comments:

Post a Comment