Precast concrete sealing underway to Bean Hall- Some marking from insitu work to be cleaned prior to seal- In case a deep clean is required, use Lithofin MN Power-Clean diluted 1:20 and a white pad. (tech sheet issued 10.02.15)
Bean door screen BE.EW.00.07- opening appears too small/ straps bent. HCL to advise
Bean curtain wall screen/ door BE.ED.00.04. Gaps either side of screen 25-30mm. HCL to advise how this gap will be closed as current discrepancy between screen and opening.
Ditto
Screed to lower landing of seminar stair now complete
Bean GFL drylining GL B/3- insulation missing- HCL to address to all areas
Bean head detail to seminar stair:
- Partition not fixed at 600mm centres as required
- Not adequate fire or acoustic separation
- Unistrut continuing through spaces
HCL to address all
Bean seminar stair walls- ensure adequate acoustic and firestopping. Head detail currently unacceptable. HCL to address
Ditto
Airtightness. Gaps to airtight ceiling where interface with structure. HCL to address
Bean 1FL window BE.EW.01.05:
- Cill and head installed at incorrect height- refer details 0331 BE.13.6- HCL to address
- LAC painted onto external face brickwork- unacceptable- HCL to address
Bean 1FL window BE.EW.01.05:
- RIW DPC continuous from cill/ lapped under capping detail- not as built- refer details 0331 BE.13.6. HCL to address
Arched windows- brickwork and concrete beyond specified tolerances. HCL to advise how this will be addressed.
BE.EW.01.09 + BE.EW.01.10- window frames installed before arches have been pointed. Work out of sequence. HCL to advise of method to address and provide acceptable finish without damage to installed frame
Ditto
Installed window frames unprotected as brickwork built overhead. Unacceptable- HCL to advise ho to address
Airtightness- large voids in interfaces with services and structure- HCL to address
Ditto
Bean refurb. Mist coat decs commenced but existing electrical services have not been removed- see below
Old emergency fittings to be removed prior to decoration- works out of sequence. HCL to address
Raised floors- installation underway 1FL Cunliffe
1FL Cunliffe- plaster beads installation underway
2FL Cunliffe- Data cabling underway- although building is not watertight.
Plastering underway to 2FL Cunliffe- CU.02.06
Ditto
Ditto
Partition to CU.02.05- ensure gaps sealed between substrates prior to plastering- HCL to address
CU.02.05- awaiting plastering- refer notes above for acoustics
Additional cill formed over bauder to Cunliffe window CU.EW.02.11. HCL to advise how this will be addressed.
Hit and miss brickwork Cunliffe north elevation GFL high level:
- Soft joint to be formed to interface with brickshield.
- Ties required as F30/212- not currently installed- refer plan drawing CU.11.2.
- Retrofit solution may now be required. HCL to advise. To be addressed before ductwork installation.
- HCL to confirm cavity tray installation carried out to all openings as detail CU 11.2
Cunliffe brickshield north and east elevations. Quality of setting of slips unacceptable. Mortar joints variable/ faces of slips not flush. Slips also falling off. HCL to address. CVA to reattend for further review of quality and finish.
Ditto
Ditto
Cill detail very poor.
Areas of brickshield condemned- refer above. HCL to address,. CVA to reattend site to review.