Wednesday, 11 March 2015

Site Visit 10.03.15

 Precast concrete sealing underway to Bean Hall- Some marking from insitu work to be cleaned prior to seal- In case a deep clean is required, use Lithofin MN Power-Clean diluted 1:20 and a white pad. (tech sheet issued 10.02.15)

 Bean door screen BE.EW.00.07- opening appears too small/ straps bent. HCL to advise

Bean curtain wall screen/ door BE.ED.00.04. Gaps either side of screen 25-30mm. HCL to advise how this gap will be closed as current discrepancy between screen and opening.

 Ditto

 Screed to lower landing of seminar stair now complete

 Bean GFL drylining GL B/3- insulation missing- HCL to address to all areas

 Bean head detail to seminar stair:
  • Partition not fixed at 600mm centres as required
  • Not adequate fire or acoustic separation
  • Unistrut continuing through spaces
HCL to address all
 Bean seminar stair walls- ensure adequate acoustic and firestopping. Head detail currently unacceptable. HCL to address
 Ditto

 Airtightness. Gaps to airtight ceiling where interface with structure. HCL to address

 Bean 1FL  window BE.EW.01.05:
  • Cill and head installed at incorrect height- refer details 0331 BE.13.6- HCL to address
  • LAC painted onto external face brickwork- unacceptable- HCL to address
 Bean 1FL  window BE.EW.01.05:
  • RIW DPC continuous from cill/ lapped under capping detail- not as built- refer details 0331 BE.13.6. HCL to address
Arched windows- brickwork and concrete beyond specified tolerances. HCL to advise how this will be addressed.
 BE.EW.01.09 + BE.EW.01.10- window frames installed before arches have been pointed. Work out of sequence. HCL to advise of method to address and provide acceptable finish without damage to installed frame

 Ditto

 Installed window frames unprotected as brickwork built overhead. Unacceptable- HCL to advise ho to address

 Airtightness- large voids in interfaces with services and structure- HCL to address

 Ditto

 Bean refurb. Mist coat decs commenced but existing electrical services have not been removed- see below
 Old emergency fittings to be removed prior to decoration- works out of sequence. HCL to address

 Raised floors- installation underway 1FL Cunliffe

 1FL Cunliffe- plaster beads installation underway

 2FL Cunliffe- Data cabling underway- although building is not watertight.

 Plastering underway to 2FL Cunliffe- CU.02.06

 Ditto

 Ditto

 Partition to CU.02.05- ensure gaps sealed between substrates prior to plastering- HCL to address

 CU.02.05- awaiting plastering- refer notes above for acoustics

 Additional cill formed over bauder to Cunliffe window CU.EW.02.11. HCL to advise how this will be addressed.

 Hit and miss brickwork Cunliffe north elevation GFL high level:
  • Soft joint to be formed to interface with brickshield.
  • Ties required as F30/212- not currently installed- refer plan drawing CU.11.2. 
  • Retrofit solution may now be required. HCL to advise. To be addressed before ductwork installation.
  • HCL to confirm cavity tray installation carried out to all openings as detail CU 11.2

 Cunliffe brickshield north and east elevations. Quality of setting of slips unacceptable. Mortar joints variable/ faces of slips not flush. Slips also falling off. HCL to address. CVA to reattend for further review of quality and finish.

 Ditto

 Ditto

 Cill detail very poor.

Areas of brickshield condemned- refer above. HCL to address,. CVA to reattend site to review.