Ditto
1FL triangular roof covering- 1st layer laid prior to remedial cavity tray works on squint wall
Cavity tray to be installed to 1FL squint wall where currently omitted
BE.EW.00.04 Cill level/ timber too high- to be adjusted. Action HCL
Bean roof- parapet return GL 3. HCL to strip back roof and forward proposal for remedial works to rectify.
Cunliffe 2FL dormer linings underway.
Cunliffe 2FL window CU.EW.02.07 airtightness to be maintained. EDPM short of final lintel.
Action HCL
Builderswork 1FL Riser 3. Acoustic and structural floor infill required. HCL to advise of proposal
Airtightness issue high level Bean 1FL GL 3/A adjacent lft shaft. linings/ sealant to be sufficient in all areas.
Ditto 1FL Bean GL 2/A ceiling
HCL to amend wall where built over cavity/ forward revised secondary steel detail/ fixing to BE.EW.01.05
Ditto
Fineline arch window frames- tolerance of concrete outside structural engineers requirements. HCL to forward details of how linings will be formed to accommodate this discrepancy.
Cunliffe Steelwork. Intumescent paintwork to be completed where obscured previously by scaffolding (Building Control comment)
CU.ED.00.01- cylinder installed on final fire escape door- not as comments. HCL to address
Ditto
Plasterboard wet in Bean GFL toilets- to be replaced.
Cunliffe 2FL linings underway