Wednesday, 25 February 2015

Site Visit 17 + 24.02.15



Cunliffe 2FL gyproc framing awaiting linings
 
Brickwork to CU.EW.00.07 to be reviewed- opening not as CVA dwg/ Alucraft doors sizing issue

Ductwork to cavities to be installed- existing installation will need to be removed in lieu of duct

Screed installed/ concrete bases/ mist coat to soffit- Cunliffe plantroom

Awaiting outlets to screed- laid to falls- Cunliffe plant room

Head detail to be reviewed by British Gyspum- running under unistrut frame. Fixings inadequate. Action HCL

Ditto

Alucraft details require review to Link glazing. CVA to issue correspondence to HCL regarding details which are not in compliance with those agreed during VE Stage

CU.EW.00.02 window openings do not have 10mm tolerance for window- HCL to advise

Ditto

Ditto windows CU.EW.02.02, 03, 04, 05. HCL to advise

Mist coat applied to GFL Bean ceiling

Arches to arcade. 1 No. rebuilt, 2 No. remaining

Bulkhead to be formed around services GFL Bean refurb

BE.EW.01.05 brickwork bridging cavity which is unacceptable. Secondary structure connection to be revised- HCL to advise

Cavity to be 50mm minimum to comply with building regs BE.EW.01.05- HCL to advise

2 plasterbaords min coverage to steels as details- HCL to address.

Structural concrete tolerances beyond specification. Packing 30-40mm. HCL to advise regarding linings/ mastic method statement/ detail

 
Ditto

Parapet detail/ setting out to be reviewed. South elevation brickwork incorrect. HCL to advise of remedial works to correct.

Cunliffe 2FL gables. linings internally to be symmetrical as advise on site- not as framing currently installed. HCL to address
Cunliffe lintols to windows CU.EW.01.02, 03, 04, 05 set out incorrectly. HCL to advise of remedial works to correct.
Cunliffe south elevation overview. Errors to setting out- refer above

Ditto

Parapet detail Cunliffe south elevation. Setting out of gutters incorrect. HCL to advise of remedial works to correct.