Friday, 13 February 2015

Site Visit 05+09+12.02.15

Bean LRC- GFL arch window installation underway

Cunliffe brickshield ongoing

Cunliffe Sanatorium- plasterboard tilebacker board where plastered finish required- CVA to liaise with HCL regarding finishes

Paint finishes samples carried out- schedules all updated with colours/ finishes following client approval
Bean LRC overview

Cunliffe brickshield- adhesive over slips- to be removed/ slips replaced- Action HCL

Ditto

Brickwork support installation underway for hit and miss panels to Cunliffe GFL

Area for movement joint between brickshield and brickwork


Insulation to be adapted where openings incorrect- Cunliffe 1FL- Action HCL

HCL to check fixing for gutter detail. Ply detail not as CVA drawings. HCL to advise

Bauder roof- pooling still apparent to Bean LRC roof- awaiting mods to outlet areas

Condemned: Lantern detail- Bean LRC roof. :
  • VCL installed incorrectly
  • Insulation burnt
  • Slates set out incorrectly
  • Secondary steelwork for glazing incorrect
HCL to advise of programme of remedial works to address all of above issues

Lantern detail- Bean LRC roof. Ditto

Lantern detail- Bean LRC roof. Ditto

Lantern detail- Bean LRC roof. Ditto

Lantern detail- Bean LRC roof. Ditto

Parapet detail incorrect to Bean LRC roof. To be addressed. HCL to advise

Ditto

Condemned: Bean 1FL Arch BE.EW.01.04 Mortar joint/ cuts around arch to be addressed. Not as
reference panel. HCL to address

Ditto
Ditto BE.EW.01.03. HCL to address

Cunliffe 2FL lintol adjusted to CU.ED.02.01. HCL to raise COI

Cunliffe 2FL linings. Dormer linings to be symmetrical. Action HCL

2FL raised floor system underway- Cunliffe

Cunliffe 2FL- linings underway to classrooms