Stage lawn not to be used for storage of materials. All to be removed and compound formed as tender documents
Refectory opening formed poorly and damaged. To be rebuilt with sufficient framing/ strength
Lining to Cunliffe top floor- CVA to confirm internal geometry
Bulkhead lining construction underway- top floor Cunliffe classrooms
Ditto
Mortar applied to brickshield area- comparison with red mortar now apparent- acceptable constrast
Brickwork repairs- further sample formed with dye- lower right area of image acceptable to client.
Cunliffe 2FL opening formed for CU.ED.02.01. Upstand exposed to cill level.
Cunliffe 2FL opening formed for CU.ED.02.01. Upper lintol to be repositioned to allow current opening to be retained
Bean LRC roof- interface between roof plant enclosure and parapet wall built incorrectly. HCL to refer
4Bay to rectify height of brickwork support steelwork- set at incorrect height. HCL to advise
Ditto
Special cavity tray now installed to 1FL Bean LRC arched openings
CVA to confirm support to cavity- Cunliffe drawings refer to metsec frame
Ditto
Cunliffe service risers- HCL builderswork openings not as OR builderswork. HCL to provide grille or appropriate guarding- HCL to advise/ confirm
AC units to corridors. Bower Fuller to provide spigot connection details. CVA to update design intent in lieu of site fabricated upper panels.
Cunliffe- GFL + 1FL soffit repairs still to be carried out- M&E installation already in progress- works out of sequence. Care to be taken to protect or remove all equipment during making good works. CVA to monitor. HCL to forward method statement. Action HCL
Window installation- Alucraft windows all include restrictor control obstructing proposed lining. Not included in drawings or commented on. Alucraft to forward alternative location/ control. HCL to confirm that fixings will be suitably sealed and hidden by linings in all locations. Action HCL
HCL to provide insulation where timber reveal build out not solid. Air tightness detailing to be carried out to all windows/ reveals in both new build and refurb Cunliffe building. Action HCL
First fix electrical services installed in Cunliffe in lieu of raised floor system. Areas to be cleared prior to installation. Action HCL
Tile backer board used to both faces of sanitorium. Not as Specification K10/ 110F which stipulates 1 No. layer wallboard to outer face and tile backer board to inner face. HCL to address. Action HCL
Profile to be added over openings to Brickshield north elevation- Action HCL
Insulation setting out incorrect to 1FL reveals- HCL to advise how to address- Action HCL
Existing openings to be blocked up prior to application of further insulation- Cunliffe North elevation
-Action HCL
awaiting brickshield/ cill pressing- Cunliffe north elevation
Temporary waterproofing to roof of flat roof dormer/ awaiting windows/ pressed metal roof- Cunliffe north elevation
Internal partition to be formed between stair/ staffroom- Action HCL
Drylining to be added internal to line stairwell/ dormer- Action HCL
Roof tile sorting still to be reviewed- Cunliffe north elevation
Bauder roof ongoing- Bean LRC link
Cunliffe eaves detail to be completed in brickwork in lieu of brickshield insulation- Action HCL
Ditto