Cunliffe 2FL gyproc framing awaiting linings
Ductwork to cavities to be installed- existing installation will need to be removed in lieu of duct
Screed installed/ concrete bases/ mist coat to soffit- Cunliffe plantroom
Awaiting outlets to screed- laid to falls- Cunliffe plant room
Head detail to be reviewed by British Gyspum- running under unistrut frame. Fixings inadequate. Action HCL
Ditto
Alucraft details require review to Link glazing. CVA to issue correspondence to HCL regarding details which are not in compliance with those agreed during VE Stage
CU.EW.00.02 window openings do not have 10mm tolerance for window- HCL to advise
Ditto
Ditto windows CU.EW.02.02, 03, 04, 05. HCL to advise
Mist coat applied to GFL Bean ceiling
Arches to arcade. 1 No. rebuilt, 2 No. remaining
Bulkhead to be formed around services GFL Bean refurb
BE.EW.01.05 brickwork bridging cavity which is unacceptable. Secondary structure connection to be revised- HCL to advise
Cavity to be 50mm minimum to comply with building regs BE.EW.01.05- HCL to advise
2 plasterbaords min coverage to steels as details- HCL to address.
Structural concrete tolerances beyond specification. Packing 30-40mm. HCL to advise regarding linings/ mastic method statement/ detail
Ditto
Parapet detail/ setting out to be reviewed. South elevation brickwork incorrect. HCL to advise of remedial works to correct.
Cunliffe 2FL gables. linings internally to be symmetrical as advise on site- not as framing currently installed. HCL to address
Cunliffe lintols to windows CU.EW.01.02, 03, 04, 05 set out incorrectly. HCL to advise of remedial works to correct.
Cunliffe south elevation overview. Errors to setting out- refer above
Ditto
Parapet detail Cunliffe south elevation. Setting out of gutters incorrect. HCL to advise of remedial works to correct.