Wednesday, 25 February 2015

Site Visit 17 + 24.02.15



Cunliffe 2FL gyproc framing awaiting linings
 
Brickwork to CU.EW.00.07 to be reviewed- opening not as CVA dwg/ Alucraft doors sizing issue

Ductwork to cavities to be installed- existing installation will need to be removed in lieu of duct

Screed installed/ concrete bases/ mist coat to soffit- Cunliffe plantroom

Awaiting outlets to screed- laid to falls- Cunliffe plant room

Head detail to be reviewed by British Gyspum- running under unistrut frame. Fixings inadequate. Action HCL

Ditto

Alucraft details require review to Link glazing. CVA to issue correspondence to HCL regarding details which are not in compliance with those agreed during VE Stage

CU.EW.00.02 window openings do not have 10mm tolerance for window- HCL to advise

Ditto

Ditto windows CU.EW.02.02, 03, 04, 05. HCL to advise

Mist coat applied to GFL Bean ceiling

Arches to arcade. 1 No. rebuilt, 2 No. remaining

Bulkhead to be formed around services GFL Bean refurb

BE.EW.01.05 brickwork bridging cavity which is unacceptable. Secondary structure connection to be revised- HCL to advise

Cavity to be 50mm minimum to comply with building regs BE.EW.01.05- HCL to advise

2 plasterbaords min coverage to steels as details- HCL to address.

Structural concrete tolerances beyond specification. Packing 30-40mm. HCL to advise regarding linings/ mastic method statement/ detail

 
Ditto

Parapet detail/ setting out to be reviewed. South elevation brickwork incorrect. HCL to advise of remedial works to correct.

Cunliffe 2FL gables. linings internally to be symmetrical as advise on site- not as framing currently installed. HCL to address
Cunliffe lintols to windows CU.EW.01.02, 03, 04, 05 set out incorrectly. HCL to advise of remedial works to correct.
Cunliffe south elevation overview. Errors to setting out- refer above

Ditto

Parapet detail Cunliffe south elevation. Setting out of gutters incorrect. HCL to advise of remedial works to correct.




Friday, 13 February 2015

Site Visit 05+09+12.02.15

Bean LRC- GFL arch window installation underway

Cunliffe brickshield ongoing

Cunliffe Sanatorium- plasterboard tilebacker board where plastered finish required- CVA to liaise with HCL regarding finishes

Paint finishes samples carried out- schedules all updated with colours/ finishes following client approval
Bean LRC overview

Cunliffe brickshield- adhesive over slips- to be removed/ slips replaced- Action HCL

Ditto

Brickwork support installation underway for hit and miss panels to Cunliffe GFL

Area for movement joint between brickshield and brickwork


Insulation to be adapted where openings incorrect- Cunliffe 1FL- Action HCL

HCL to check fixing for gutter detail. Ply detail not as CVA drawings. HCL to advise

Bauder roof- pooling still apparent to Bean LRC roof- awaiting mods to outlet areas

Condemned: Lantern detail- Bean LRC roof. :
  • VCL installed incorrectly
  • Insulation burnt
  • Slates set out incorrectly
  • Secondary steelwork for glazing incorrect
HCL to advise of programme of remedial works to address all of above issues

Lantern detail- Bean LRC roof. Ditto

Lantern detail- Bean LRC roof. Ditto

Lantern detail- Bean LRC roof. Ditto

Lantern detail- Bean LRC roof. Ditto

Parapet detail incorrect to Bean LRC roof. To be addressed. HCL to advise

Ditto

Condemned: Bean 1FL Arch BE.EW.01.04 Mortar joint/ cuts around arch to be addressed. Not as
reference panel. HCL to address

Ditto
Ditto BE.EW.01.03. HCL to address

Cunliffe 2FL lintol adjusted to CU.ED.02.01. HCL to raise COI

Cunliffe 2FL linings. Dormer linings to be symmetrical. Action HCL

2FL raised floor system underway- Cunliffe

Cunliffe 2FL- linings underway to classrooms