Bean GFL Arcade- HCL to ensure mortar infill to all brickwork- this has not been adhered to thus far- remedial work required to pier construction
Arch formers to arcade underway
Ditto
Steelwork to Bean roof- underway on site. Concrete recess formed to take steel beam. Void not formed in concrete as original HRW specification so remedial works taking place on site.
Additional steel connection required to lift shaft- action HRW
Cunliffe roof- carpentry/ rooflight openings formed
Ditto
Steelwork to west elevation now installed
Ditto
Bean stair amendments ongoing
Cunliffe brickwork to GL 7 A-B GFL- brick cleaning sample insufficient/ unacceptable. Stripes of marked headers still apparent. HCL to address or rebuild.
Valley construction underway to Bean roof. RL.02.08 opening formed incorrectly/ orientation wrong. CVA to forward setting out
Gutter line GL 7 F-G 2FL. CVA to review build up to maintain 150mm clear.
Cunliffe roof GL 7/G- packing of steel/ fixing to be addressed
2FL Cunliffe classrooms- carpentry to roof underway
Cunliffe Valley rooflight opening 2FL
Bean Steel interface issue- connection amendment required GL 4/ A-B
Ditto
Bean Library 1FL- West side
Seminar stair
Bean 1FL GL 3/C-D. Existing brickwork cill detail to be made good following steel column installation. Cill bricks to be salvaged when existing window opening dropped to form doorway
Ditto at high level. Corbelled courses of brickwork are exposed and breaking out will need repair. Action HCL
Tuesday, 26 August 2014
Friday, 15 August 2014
Site visit 14.08.14
Bean overview
Scaffold underway in prep for arch construction to arcade
Set out issue with window to refectory- minor adjustment required to metsec- discussed on site
nibs G/L 1 to be rebuilt- not plumb
Ditto
Arch G/L D- brickwork removed in lieu of BPW arch cavity tray
Brickwork movement joint G/L D/ 2-3
Cornish concrete response still required for structural topping/ infill to precast elements
Carpentry underway to Cunliffe Roof
Ditto
Rooflight openings formed to Cunliffe roof
HRW to issue advice regarding base plates to 2FL steelwork Cunliffe
Ditto
Cunliffe north elevation 2FL
CVA to review potential clash between window and stair lining 1FL landing Cunliffe new stair
Metsec detail around downpipe- CVA to review Purkiss details
Survey of levels required from HCL- discrepancy between existing/ proposed 1st floor cunliffe
Brickwork G/L 7/ A-B- cleaned brickwork- headers still marked/ orange
Ditto
Possible clash of Alucraft profile adjacent link where VE to glazing- CVA to investigate further and report back
Hutton to order special handmade brick to Bean arch- refurb. Refer earlier SVR notes
Scaffold underway in prep for arch construction to arcade
Set out issue with window to refectory- minor adjustment required to metsec- discussed on site
nibs G/L 1 to be rebuilt- not plumb
Ditto
Arch G/L D- brickwork removed in lieu of BPW arch cavity tray
Brickwork movement joint G/L D/ 2-3
Cornish concrete response still required for structural topping/ infill to precast elements
Carpentry underway to Cunliffe Roof
Ditto
Rooflight openings formed to Cunliffe roof
HRW to issue advice regarding base plates to 2FL steelwork Cunliffe
Ditto
Cunliffe north elevation 2FL
CVA to review potential clash between window and stair lining 1FL landing Cunliffe new stair
Metsec detail around downpipe- CVA to review Purkiss details
Survey of levels required from HCL- discrepancy between existing/ proposed 1st floor cunliffe
Brickwork G/L 7/ A-B- cleaned brickwork- headers still marked/ orange
Ditto
Possible clash of Alucraft profile adjacent link where VE to glazing- CVA to investigate further and report back
Hutton to order special handmade brick to Bean arch- refurb. Refer earlier SVR notes
Monday, 11 August 2014
Site visit 08.08.14
Remaining Arch corner sample reference panel now complete. CVA to forward comments to HCL
Detail to external face of panel with some poor areas of pointing
Specials on site for corner G/L D
Special angled bricks
Corner G/L D with reinforcement installation
Ditto
Amendments to Bean stair/ landing underway
Cunliffe Steel frame- Metsec infill to top floor installed
Ditto
Detail- Cunliffe metsec frame
Bean G/L A/1 arch before spring points
Scaffold may need to extend onto stage. HCL to advise of extent
Brickwork to G/L 1- not plumb- to be taken down and rebuilt
Ditto
Detail of reinforcement to corner Bean G/L A. HCL to ensure full fill of mortar between bricks
Progress of piers to arches below spring point to arcade
Progress to arcade. CVA to review spring point level discrepancy between elevations.
Cut bricks to Cunliffe laid G/L 7/A-B GFL covered in dust from on-site cutting. Method to be reviewed. Bricks to be cleaned for further site inspection on Thursday 14th Aug.
Further bricks to Cunliffe G/L 7/F-G where cutting method modified and less dust to header face.
Detail to external face of panel with some poor areas of pointing
Specials on site for corner G/L D
Special angled bricks
Corner G/L D with reinforcement installation
Ditto
Amendments to Bean stair/ landing underway
Cunliffe Steel frame- Metsec infill to top floor installed
Ditto
Detail- Cunliffe metsec frame
Bean G/L A/1 arch before spring points
Scaffold may need to extend onto stage. HCL to advise of extent
Brickwork to G/L 1- not plumb- to be taken down and rebuilt
Ditto
Detail of reinforcement to corner Bean G/L A. HCL to ensure full fill of mortar between bricks
Progress of piers to arches below spring point to arcade
Progress to arcade. CVA to review spring point level discrepancy between elevations.
Cut bricks to Cunliffe laid G/L 7/A-B GFL covered in dust from on-site cutting. Method to be reviewed. Bricks to be cleaned for further site inspection on Thursday 14th Aug.
Further bricks to Cunliffe G/L 7/F-G where cutting method modified and less dust to header face.
Subscribe to:
Comments (Atom)