Sunday, 3 August 2014

Site visit 01.08.14

 Bean LRC overview

 G/L A1 brickwork to be adapted due to omission of reinforcement

 Ditto

 Ditto

 GFL relief arch underway
 Ditto

 Ditto

 West Elevation brickwork underway

 Bean LRC stair mods still required

 Infill 1FL slab - awaiting HRW clarification

 Scabbling to arches complete- awaiting remedials in Fosroc

 Ditto- projecting reinforcement

 Packing to steel support Cunliffe 2FL- HRW/ CVA review where levels different from survey

 Ditto

 Cunliffe 2FL steelwork erected

 Baseplates to be adapted where projecting into insulation zone

 Ditto

 Disparity between Metsec and concrete frame setting out Cunliffe south Elevation- HCL to advise

Ditto

 Ditto

 Glazed brick Cunliffe GFL- chip to corner brick to be removed

 opposite return ok
 Glazed brick recess panel to Cunliffe south elevation

 Ditto

 CVA to check 0.00m level/ brickwork setting out

 RE: Cunliffe Metsec set out- action HCL

 Concrete projecting into insulation/ cavity zone- HCL to advise

 RWP hole too small 2FL Cunliffe steel frame

 Cunliffe stair- dormer frame

 Cunliffe GFL blockwork to plant enclosure underway

 Cunliffe steel/ south elevation overview

 Bean LRC north elevation concrete/ column set out disparity- HCL to advise