Bean GFL Arcade- HCL to ensure mortar infill to all brickwork- this has not been adhered to thus far- remedial work required to pier construction
Arch formers to arcade underway
Ditto
Steelwork to Bean roof- underway on site. Concrete recess formed to take steel beam. Void not formed in concrete as original HRW specification so remedial works taking place on site.
Additional steel connection required to lift shaft- action HRW
Cunliffe roof- carpentry/ rooflight openings formed
Ditto
Steelwork to west elevation now installed
Ditto
Bean stair amendments ongoing
Cunliffe brickwork to GL 7 A-B GFL- brick cleaning sample insufficient/ unacceptable. Stripes of marked headers still apparent. HCL to address or rebuild.
Valley construction underway to Bean roof. RL.02.08 opening formed incorrectly/ orientation wrong. CVA to forward setting out
Gutter line GL 7 F-G 2FL. CVA to review build up to maintain 150mm clear.
Cunliffe roof GL 7/G- packing of steel/ fixing to be addressed
2FL Cunliffe classrooms- carpentry to roof underway
Cunliffe Valley rooflight opening 2FL
Bean Steel interface issue- connection amendment required GL 4/ A-B
Ditto
Bean Library 1FL- West side
Seminar stair
Bean 1FL GL 3/C-D. Existing brickwork cill detail to be made good following steel column installation. Cill bricks to be salvaged when existing window opening dropped to form doorway
Ditto at high level. Corbelled courses of brickwork are exposed and breaking out will need repair. Action HCL