Monday, 11 August 2014

Site visit 08.08.14

 Remaining Arch corner sample reference panel now complete. CVA to forward comments to HCL

 Detail to external face of panel with some poor areas of pointing

 Specials on site for corner G/L D

Special angled bricks

  Corner G/L D with reinforcement installation

Ditto

 Amendments to Bean stair/ landing underway

 Cunliffe Steel frame- Metsec infill to top floor installed

 Ditto

 Detail- Cunliffe metsec frame

Bean G/L A/1 arch before spring points

 Scaffold may need to extend onto stage. HCL to advise of extent

 Brickwork to G/L 1- not plumb- to be taken down and rebuilt

 Ditto

 Detail of reinforcement to corner Bean G/L A. HCL to ensure full fill of mortar between bricks

 Progress of piers to arches below spring point to arcade

 Progress to arcade. CVA to review spring point level discrepancy between elevations.

Cut bricks to Cunliffe laid G/L 7/A-B GFL covered in dust from on-site cutting. Method to be reviewed. Bricks to be cleaned for further site inspection on Thursday 14th Aug.

Further bricks to Cunliffe G/L 7/F-G where cutting method modified and less dust to header face.