Remaining Arch corner sample reference panel now complete. CVA to forward comments to HCL
Detail to external face of panel with some poor areas of pointing
Specials on site for corner G/L D
Special angled bricks
Corner G/L D with reinforcement installation
Ditto
Amendments to Bean stair/ landing underway
Cunliffe Steel frame- Metsec infill to top floor installed
Ditto
Detail- Cunliffe metsec frame
Bean G/L A/1 arch before spring points
Scaffold may need to extend onto stage. HCL to advise of extent
Brickwork to G/L 1- not plumb- to be taken down and rebuilt
Ditto
Detail of reinforcement to corner Bean G/L A. HCL to ensure full fill of mortar between bricks
Progress of piers to arches below spring point to arcade
Progress to arcade. CVA to review spring point level discrepancy between elevations.
Cut bricks to Cunliffe laid G/L 7/A-B GFL covered in dust from on-site cutting. Method to be reviewed. Bricks to be cleaned for further site inspection on Thursday 14th Aug.
Further bricks to Cunliffe G/L 7/F-G where cutting method modified and less dust to header face.