Friday, 15 August 2014

Site visit 14.08.14

 Bean overview

 Scaffold underway in prep for arch construction to arcade

 Set out issue with window to refectory- minor adjustment required to metsec- discussed on site

 nibs G/L 1 to be rebuilt- not plumb

 Ditto

 Arch G/L D- brickwork removed in lieu of BPW arch cavity tray

 Brickwork movement joint G/L D/ 2-3

 Cornish concrete response still required for structural topping/ infill to precast elements

 Carpentry underway to Cunliffe Roof

 Ditto

 Rooflight openings formed to Cunliffe roof

 HRW to issue advice regarding base plates to 2FL steelwork Cunliffe

 Ditto

 Cunliffe north elevation 2FL

 CVA to review potential clash between window and stair lining 1FL landing Cunliffe new stair

 Metsec detail around downpipe- CVA to review Purkiss details

 Survey of levels required from HCL- discrepancy between existing/ proposed 1st floor cunliffe

 Brickwork G/L 7/ A-B- cleaned brickwork- headers still marked/ orange

 Ditto

Possible clash of Alucraft profile adjacent link where VE to glazing- CVA to investigate further and report back
Hutton to order special handmade brick to Bean arch- refurb. Refer earlier SVR notes