 Cunliffe/ Bean refurb overview. Temporary roof being removed

 Bean LRC overview

 Arch GL/ A demolished- to be rebuilt at correct spring height. All reinforcement to be reinstated as originally specified. Action HCL

 Bricks cannot be salvaged- HCL confirm that 20000 No. additional bricks secured. All reinforcement to be reinstated as originally specified. Action HCL

 Stair BE.00.11. Bottom tread/ stair set too low. HCL to raise. Also screed not set for matwell recess as required. HCL to adjust

 Further adjustment required to screeds/ levels GFL BeanLRC / Bean refurb. Action HCL

 CVA to instruct minor area of render to be carefully removed adjacent BE.ED.00.04.

 Bean 1FL airtight ceilings. Mastic seal/ full board coverage required to form air tightness line. HCL to address throughout
Bean 1FL GL 1/A- air tightness detail not achieved to corner. Further boarding/ mastic required.  HCL to address throughout


Water damaged boards retained and overboarded- HCL to address. Action HCL

Brickwork to be adjusted to window opening reveal BE.EW.01.06

Ditto

Grout to be removed from facing brickwork adjacent BE.EW.01.04

Intermediate arches to be removed and rebuilt at correct spring point height.

Corner detail to arcade

Parapet to arcade

Services penetration builderswork close to glazing within link- CVA to check

Ditto

Intumescent paintwork to be carried out prior to services installation. HCL to advise of programme

Containment fitted to 1FL demi-deck soffits

Ditto

Infill masonry/ making good required to Cunliffe 2FL stairwell

Level changes/ screed issues to be reported on 2FL Cunliffe. Discrepancy between stair landing and required raised floor voids. Action HCL

Insulation to Cunliffe roof to be addressed. Loose panels still apparent. U value not achieved. Action HCL

Brick/ lintol added to openings in lieu of cement slurry mix BE.IW.01.02,3

4 No. courses of brickshield slips laid poorly. To be removed and relaid level. Action HCL

Ditto

Cable route to main school reviewed. CVA to liaise with OR regarding route confirmation- Action CVA/ OR

Bean roof refurb- CVA to instruct infill timber to eaves detail.


Gutter to be monitored with view to setting forward/ lower.


Tiles mismatch to north face Bean roof refurb. To be adjusted- Action HCL

CU.EW.01.16- head level to be confirmed- Action CVA.

Flashings to be completed- Bean refurb roof

Cunliffe brickwork south elevation- underway 1FL

Bean refurb. Brick repair samples. To be toned back/ reviewed with client

Ditto

Plasterboard water damaged before fitting GFL Cunliffe CU.00.10. To be replaced- Action HCL

Ditto

Ditto

CVA to confirm continuation of dado trunking to return wall to enable feed to external wall- CU.00.12. Action CVA