Site visit 12.06.15

 Bean Seminar stair- awaiting secondary ceiling frame

 Arch return adjacent Cunliffe- brick/ mortar still to be made good/ addressed- not as reference panel

 Awaiting soffit panelling to interface between arches and link

 Brickshield to Cunliffe under link- profile carrying cladding bent- to be adjusted before final insulation/ slips applied- Action HCL
 Ditto.Also ensure adequate space for build up of sub base, mortar bedding and slab- Action HCL

Bean refurb- arch removed in error due to be rebuilt

Bean LRC overview

Arcade awaiting panelling, rooflights and landscape. Brick remedials/ cleaning  still to be carried out- Action HCL
RWP now moved to allow clearance for soffit cladding panels in trespa

Relocated radiator/ dado acceptable in Marshall's room. Allowance for 1400 desk

Water fountain to be installed at 900mm AFFL. Currently installed at 1000 AFFL- Action HCL

Brick wall underway to modified window opening BE.EW.00.11- Action HCL

Ceiling to stop short in lieu of archive display joinery- Action HCL

Precast concrete soffits to Bean Hall now with lights installed. Awaiting acoustic panels and perforated metal panels- Action HCL

Interface between precast concrete stair and slab. Acoustic and fire rated partition/ soffit to be formed. Cannot be achieved with bulkhead to be built beneath.- Action HCL

Servery duct rising onto roof avoiding 1FL roof gulley. Additional fire rated compartment to be formed to ceiling.- Action HCL
All redundant cables to be removed- Action HCL

Bean LRC 1st FLR overview

Laminate doors still not protected- Action HCL

Steel frame glazed doors unprotected- Action HCL

Acoustic panels installed 1st floor Cunliffe

Metal hatches installed 1st + 2nd floor Cunliffe

Cunliffe 2FL staff room- remedial works required to walls- Action HCL

Ventilation joinery panel installation underway 2FL- Action HCL

Cunliffe brickshield to Cunliffe 2FL adjacent link still to be carried out- Action HCL

Cunliffe laminate doors 2FL- unprotected and now marked- Action HCL

Slot drain installed to BE.ED.00.07

Now awaiting storm proof louvre installation

Bolt to Cunliffe stair crooked- ensure adequate fixing- Action HCL

Face fixed smoke head installed to Cunliffe rooflight 2FL