Bean GFL BE.ED.00.04- no cavity closer/ insulation to cavity/ profile required to close gap between mullion and brickwork. Gap greater that Alucraft drawings as previously commented
Background heating installed to 'shop window' display BE.EW.00.11
Bean 1FL- perforated platerboard. Excessive filling to holes where planes interface. No edge beads to high level where interface with rooflight
Arcade roof awaiting sedum installation and aluminium kerb completion
Grille to Bean 1FL ceiling- clash with wall. CVA to provide additional grille to eliminate
Additional stop bead required to reveal glasroc to arches-1FL Bean. Refer BE 12.3. -Action HCL
Scaffold pole screeded-in and craked. Remedial works required- Bean 1FL link -Action HCL
Make good internal wall/ dab on plasterboard- Cunliffe CU.01.08 -Action HCL
Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL
Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL
Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL
Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL
Cunliffe 2FL riser adjacent CU.EW.02.07- ensure sealed/ airtight as previous comments/ SVR -Action HCL
Mastic to north elev Cunliffe- downpipes- poor workmanship- joint not tooled correctly- HCL to address
Ditto
Bean LRC overview
Bean arcade soffit- framing underway
Bean GFL hall- ply lining underway
Ditto
Ply lining damaged adjacent where matwells made good. HCL to address
Additional hatch formed for services access Bean GFL
Bean link joinery display case underway
Arch ventilation grilles installed Bean 1FL
BE.ID.01.05- door needs to be raised as catching on ply. Carpet still to be laid- Action HCL
Clash at head of FCUJ.03 but panel removeable to allow hatch access.
Remedial works required to back-to-back trough Cunliffe -Action HCL
CU.00.15- ceiling requires attention around hatch where ill-fitting -Action HCL
Remedial works required to window reveal CU.00.15 -Action HCL
Brickshield East elev- still incomplete. -Action HCL
Alarm to be lowered as will clash with trespa soffit/ insulation under link- Action HCL
Hard landscape underway adjacent Ashton
Brickshield/ brickwork remedials- provisional observation log to be issued by CVA -Action HCL