Monday, 20 July 2015

Site visit 13.07.15

 Bean toilets GFL- infill required between window reveal and wall/ tiling

 Bean GFL BE.ED.00.04- no cavity closer/ insulation to cavity/ profile required to close gap between mullion and brickwork. Gap greater that Alucraft drawings as previously commented

 Background heating installed to 'shop window' display BE.EW.00.11

 Bean 1FL- perforated platerboard. Excessive filling to holes where planes interface. No edge beads to high level where interface with rooflight

 Arcade roof awaiting sedum installation and aluminium kerb completion

 Grille to Bean 1FL ceiling- clash with wall. CVA to provide additional grille to eliminate

 Additional stop bead required to reveal glasroc to arches-1FL Bean. Refer BE 12.3. -Action HCL

 Scaffold pole screeded-in and craked. Remedial works required- Bean 1FL link -Action HCL

 Make good internal wall/ dab on plasterboard- Cunliffe CU.01.08 -Action HCL

 Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL

 Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL

 Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL



  Ditto Detail to lining not as CVA DWG BE 12.5. HCL to address. Refer details.-Action HCL

 Cunliffe 2FL riser adjacent CU.EW.02.07- ensure sealed/ airtight as previous comments/ SVR -Action HCL

 Mastic to north elev Cunliffe- downpipes- poor workmanship- joint not tooled correctly- HCL to address
Ditto

 Bean LRC overview

 Bean arcade soffit- framing underway

 Bean GFL hall- ply lining underway

 Ditto

 Ply lining damaged adjacent where matwells made good. HCL to address

 Additional hatch formed for services access Bean GFL

 Bean link joinery display case underway

 Arch ventilation grilles installed Bean 1FL

 BE.ID.01.05- door needs to be raised as catching on ply. Carpet still to be laid- Action HCL

 Clash at head of FCUJ.03 but panel removeable to allow hatch access.

 Remedial works required to back-to-back trough Cunliffe -Action HCL

 CU.00.15- ceiling requires attention around hatch where ill-fitting -Action HCL

 Remedial works required to window reveal CU.00.15 -Action HCL

 Brickshield East elev- still incomplete. -Action HCL

 Alarm to be lowered as will clash with trespa soffit/ insulation under link- Action HCL


 Hard landscape underway adjacent Ashton

Brickshield/ brickwork remedials- provisional observation log to be issued by CVA -Action HCL