Thursday, 2 January 2014

Site Visit 20.12.13

 Formwork for slab edge to Bean underway

 Ditto

 Blinding/ Hardcore under slab to Bean

 Cunliffe following stair removal

 Bean LRC lift pit formwork underway

1FL Cunliffe
 1FL Cunliffe- window openings temporarily covered

 Bean LRC blinding/ hardcore prior to slab pour

 Duct to stage

 Steel to 1FL Cunliffe. Cover meter survey to be carried out to slab. Removal/ replacement of steel options to be developed by HRW

 Conflict with existing steel and proposed opening underneath- to be aligned with adjacent opening

 Manhole to arcade

 Cunliffe rear elevation post- soft strip

 Bean side elevation post-soft strip

 Hardcore/ blinding in preparation for slab

Formwork preparation for lift shaft