Wednesday, 24 September 2014

Site visit 23.09.14

Plaster possibly to be removed in total to ICT office

Existing slab still protruding and visible high level to ICT classroom GFL. However within bulkhead so not visible after replastering

Cunliffe GFL survey still required following removal of existing floor finishes

Brickshield installation underway

Bean LRC west elevation overview

Brickshield installation problematic. Profile extends beyond installation

Gap cannot be made up with adhesive

Arcade north elevation.

HCL to ensure full mortar fill to all columns

Awaiting 2nd leaf construction to arches