Friday, 3 October 2014

Site Visit 02.10.14

 Arches GFL Bean underway- nearing completion

Ditto

 Cunliffe vally- bauder underway. Felt and batten underway

 Bean LRC roof- carpentry to roof deck underway

Cunliffe 2FL spaces

 Cunliffe brickshield GFL underway- profile wrong and setting out incorrect- profile to be replaced and to be mitred to reveals

 Original brick arch removed in error- HCL to replace all damge at HCL's cost

 Ditto

 Additional insulation/ support required to Cunliffe dormers 2FL

 Fixings/ grouting still incomplete to Cunliffe 2Fl steelwork

 Timber parapet infill required Cunliffe 2FL gable end

 Bauder/ felt to be overlapping- incomplete

 Roof deck incomplete/ bauder damaged/ work out of sequence Cunliffe valley gutter

 Ditto

 Valley rooflight upstand should be 150mm min high and to fall as maunfacturers recommendations

 Valley gutter parapet built too deep/ no insulation to upstand. To be redone

 Steel stub to be removed- Bean LRC roof

 Brick arcade Bean LRC GFL

 Concrete remedials Cunliffe incomplete
 Ditto

 Demidec ditto

 2FL slab treatment required- still not completed

 concrete upstand required to complete steelwork cunliffe 2FL

 Cunliffe stairs still not fixed

 ditto

 Bean refurb roof- sarking boards to be removed

 ditto

 Arch concrete scabbling required GL 1/D