Monday, 20 October 2014

Site Visit 17.10.14

Seminar stair rooflight- additional packing required due to geometry of steelwork. HRW to issue revised details

 Ditto

 Ditto

 Brick arches to northern arcade complete- scaffold lift raised

 Bean LRC roof- missing bolt connection to steel connecting plate

Cunliffe roof north face tiling-incorrectly laid tiles- taken from different pallets should be mixed on
the roof to achieve blend of colour.

Ties located to underside of Bean LRC 1FL structure- not as HRW dwgs. CVA to update airtight ceiling details

Render removed to Bean seminar stair wall- mortar repairs required and slab repair prior to cement slurry treatment

Ditto

Plasterboard installation now underway- evidence of minor water ingress still apparent

Concrete remedials also required to 1FL Cunliffe demi-dec GL B

Partition depth to be reviewed to accommodate ties 2FL Cunliffe- Action CVA

Partition Depth to stair to be as K10/ 120A. All framing constructed in this area is incorrect. Remove and rebuild as specified with deeper stud.

Ditto

Fall to rooflight adjusted

Brick cleaning to Cunliffe GFL still incomplete

Bean roof refurb- VCL applied between existing rafters. Contractor to ensure all joints taped

Ditto

Keymer tiles on site

Incorrect brickshield removed. Correct profile now on site.

Ditto

Enamelled glass sample- no comments from CVA

Diffuse glass sample- no further comments from CVA

Linto now installed 2FL Cunliffe CU.EW.02.07

Cunliffe south elevation- timber inner panel to parapet now constructed