Ditto
Ditto
Brick arches to northern arcade complete- scaffold lift raised
Bean LRC roof- missing bolt connection to steel connecting plate
Cunliffe roof north face tiling-incorrectly laid tiles- taken from different pallets should be mixed on
the roof to achieve blend of colour.
Ties located to underside of Bean LRC 1FL structure- not as HRW dwgs. CVA to update airtight ceiling details
Render removed to Bean seminar stair wall- mortar repairs required and slab repair prior to cement slurry treatment
Ditto
Plasterboard installation now underway- evidence of minor water ingress still apparent
Concrete remedials also required to 1FL Cunliffe demi-dec GL B
Partition depth to be reviewed to accommodate ties 2FL Cunliffe- Action CVA
Partition Depth to stair to be as K10/ 120A. All framing constructed in this area is incorrect. Remove and rebuild as specified with deeper stud.
Ditto
Fall to rooflight adjusted
Brick cleaning to Cunliffe GFL still incomplete
Ditto
Keymer tiles on site
Incorrect brickshield removed. Correct profile now on site.
Ditto
Enamelled glass sample- no comments from CVA
Diffuse glass sample- no further comments from CVA
Linto now installed 2FL Cunliffe CU.EW.02.07
Cunliffe south elevation- timber inner panel to parapet now constructed