Friday, 10 October 2014

Site visit 09.10.14

 Cunliffe lintols now on site

 Tiling commenced to Cunliffe north elevation roof

CVA to forward details for lining GFL Bean refurb where tile repair unfeasible

 Ditto

 CVA to liaise w/ OR regarding removal of remaining services- Bean refurb

 Insulation/ DPC detail to BE.EW.00.06

 HCL to complete remaining insulation to head

 HCL to advise regarding brickwork to GL D/1 adjacent stair 2FL Cunliffe

 Stud/ roof deck to be completed before weathertight 2FL Cunliffe

 drylined partitions commenced 1FL Cunliffe

 Ditto

 Water ingress still present 1FL Cunliffe stair. Must be completely weathertight beofre commencement of 1st fix mech/ elec

 Ply deck complete to Bean LRC- awaiting ply to rooflights

 Cunliffe G/L A-B/4 2FL. Lintol now installed and temp drainage.

 Bean LRC roof refurb- existing timbers to be neatly trimmed

 Sarking now removed
 Vent tower in situ
 Ditto trimming

 Bean brick arcade underway.

Ditto
 
 Bean LRC 1FL

View to seminar stair