Tuesday, 5 May 2015

Site visit 01.05.15


  
 Bean LRC overview

  
 1FL Bean LRC- refectory ductwork installed to lower level

 
 Transition to duct may not work with current geometry at high level within partition.

Secondary steel support to be completed- Bean LRC arch windows 1st floor

Awaiting arch formers- Bean LRC 1FL

 North elevation mortar fillet to parapet to be redone- poor quality. To be as East elevation parapet

 Awaiting bulkhead lining to be formed. CVA to confirm penetration to bulkhead face for projector

 Fire-rated screens 1FL Bean LRC- HCL to confirm strap fixing/ finish

Fire-rated screen- internal lining/ finish to seminar stair- window not flush/ detail inconsistent to perimeter- BE.IW.01.01
 Fire-rated screens 1FL Bean LRC- making good around walls required 

Ditto

 Cunliffe 2FL doors/ doorsets- head detail poor/ oversized for doorset. HCL to address

 
Ditto

 
Ditto



Ditto

 1FL Cunliffe- lights to be dropped to 400 mm below ceiling for uplighting

 Bean/ Cunliffe. Hit and miss to be redone with Cavity tray- brickpoint underway to Cunliffe

 Bean West elevation

 Clearance between last beam and arch head less than CVA detail. Clearance required for retractable screen. Also lining required for insitu concrete beam GL D- refer CVA detail BE 12.3

 Cunliffe concrete precast soffitt made good CU 01.10

 CU.ID.01.02- HCL to ensure head adequately packed/ fire-stopped

 CU.01.19 Cunliffe stair- plaster transition between wall and ceiling not straight- HCL to address


 Cunliffe CU.02.01 bulkhead/ grille misaligned- HCL to address

 Bean parapet GL d3- Still incomplete and information required from HCL regarding alternative strategy- Action HCL
 Dormer window installed but lining to be adapted to allow proper alignment with frame for airtightness
 HCL to provide details of how door will be installed/ frame/ architrave where not flush as CVA detail- Action HCL

 Opening up- Bean old stair 1FL ceiling- awaiting glasroc/ lighting

 Openings formed for light fittings old stair bean

 Insulation required to upstand as CVA detail- BE.EW.01.06

 Bead damaged- to be replaced before glass installed

 Bean 1FL- cavity tray installation to squint wall still required

 HCL to confirm where setting out not followed to seminar stair lighting as affecting HTP joinery- Action HCL

 BE.EW.01.05 installed at wrong height- timber lining to be consistent to perimeter of general reading room- HCL to step/  adjust as discussed on site

 Capping to triangle flat roof to be addressed- as earlier comments

 Cill to Marshalls office damaged- HCL to address

 Door BE.ED.00.04- escape door fitted with lock/ latch- not as comments/ CVA schedule. HCL to address.

 Window seal over door head also damaged to BE.ED.00.04- HCL to address

 Cunliffe South Elevation awaiting brick remedials. HCL to advise of method statements for lintel moving/ windposts etc. as previously requested- Action HCL

 Ditto

Timber battern/ cill pressing to be added prior to slot drain installation- CU.ED.00.08
 
Pressing end capping to be added/ flashing amended to plant enclosure Bean roof

Floor boxes 1st floor bean to be temporarily protected on site