Bean LRC overview
1FL Bean LRC- refectory ductwork installed to lower level
Transition to duct may not work with current geometry at high level within partition.
Secondary steel support to be completed- Bean LRC arch windows 1st floor
North elevation mortar fillet to parapet to be redone- poor quality. To be as East elevation parapet
Awaiting bulkhead lining to be formed. CVA to confirm penetration to bulkhead face for projector
Fire-rated screens 1FL Bean LRC- HCL to confirm strap fixing/ finish
Fire-rated screen- internal lining/ finish to seminar stair- window not flush/ detail inconsistent to perimeter- BE.IW.01.01
Fire-rated screens 1FL Bean LRC- making good around walls required
Ditto
Cunliffe 2FL doors/ doorsets- head detail poor/ oversized for doorset. HCL to address
Ditto
Ditto
Ditto
1FL Cunliffe- lights to be dropped to 400 mm below ceiling for uplighting
Bean/ Cunliffe. Hit and miss to be redone with Cavity tray- brickpoint underway to Cunliffe
Bean West elevation
Clearance between last beam and arch head less than CVA detail. Clearance required for retractable screen. Also lining required for insitu concrete beam GL D- refer CVA detail BE 12.3
Cunliffe concrete precast soffitt made good CU 01.10
CU.ID.01.02- HCL to ensure head adequately packed/ fire-stopped
CU.01.19 Cunliffe stair- plaster transition between wall and ceiling not straight- HCL to address
Cunliffe CU.02.01 bulkhead/ grille misaligned- HCL to address
Bean parapet GL d3- Still incomplete and information required from HCL regarding alternative strategy- Action HCL
Dormer window installed but lining to be adapted to allow proper alignment with frame for airtightness
HCL to provide details of how door will be installed/ frame/ architrave where not flush as CVA detail- Action HCL
Openings formed for light fittings old stair bean
Insulation required to upstand as CVA detail- BE.EW.01.06
Bead damaged- to be replaced before glass installed
Bean 1FL- cavity tray installation to squint wall still required
HCL to confirm where setting out not followed to seminar stair lighting as affecting HTP joinery- Action HCL
BE.EW.01.05 installed at wrong height- timber lining to be consistent to perimeter of general reading room- HCL to step/ adjust as discussed on site
Capping to triangle flat roof to be addressed- as earlier comments
Cill to Marshalls office damaged- HCL to address
Door BE.ED.00.04- escape door fitted with lock/ latch- not as comments/ CVA schedule. HCL to address.
Window seal over door head also damaged to BE.ED.00.04- HCL to address
Cunliffe South Elevation awaiting brick remedials. HCL to advise of method statements for lintel moving/ windposts etc. as previously requested- Action HCL
Ditto
Timber battern/ cill pressing to be added prior to slot drain installation- CU.ED.00.08