Site visit 2+14+17.04.15

 Bean BE.EW.00.06- cill brickwork incorrect- not as CVA detail- to be broken out and timber batten/ screed added prior to tile laying- Action HCL

Underway

Bean BE.EW.00.06 Fineline frame detail poor- Action HCL

Ditto

 Bean 1FL- still awaiting cavity tray installation to squint wall- Action HCL

 Cunliffe gable bricks- brick broken- overflow to be added- Action HCL

 Resin to be added under capping bricks- Cunliffe gables- Action HCL

 Cunliffe gables- making good around cappings

 OR to review external light to BE.EXED.00.01- currently recessed fitting to be respecified- Action OR

 Scaffold Struck to Bean- brickwork to be cleaned down- cappings/ movement joints adjusted

 Bean GFL Arch BE.EW.00.07- soft joint to be added

 Bean Refurb GFL- Dado overcladding in plasterboard- no flush skirting as CVA detail 0331sk623. Action HCL

 
 Bean 1FL kitchen duct riser- BF to revise kitchen extract unit and confirm duct size.

 
Builderswork not aligned with partition- 400x400 duct will not fit. Revised aspect to be proposed. To penetrate at roof level out of the gutter. Condensate wastes to also be adjusted.

 Cunliffe dormer cladding- aluminium side cladding not as drawing- diagonal sheeting/ no weathering detail. To be addressed. Also insulation face cladding/ soffit drip to be adjusted.- Action HCL

 Mock up AC panels on site 2FL Cunliffe

 Cavity tray/ducting GFL Cunliffe still to be amended- Action HCL

 Door/ window screen adjusted Cunliffe GFL CU.ED.00.04+8

MF frame installed GFL Cunliffe exam room

 
 Cunliffe south elevation- scaffold struck

 Ditto
 Cunliffe GFL- CU.00.07 Lobby handwash ceiling- insulation to ductwork to be addressed.

Cunliffe 1FL- ensure airtightness to all walls- Action HCL

 Cunliffe GFL- CU.00.07 Lobby handwash- Ceiling paintwork to be addressed/ mould addressed- Action HCL

Ditto

Bean GFL brickwork- movement joint required to plinth capping to align with wall MJ

 
GFL Bean Hall- Grilles to be installed for return air within double T beams

 Fire stopping to Old Bean services penetration 1FL- Final ceiling level below corbel

 Bean seminar stair- sail blind to be fixed to area adjacent vertical steel forming pyramid

 Bean refurb- brick reveal refurb underway

 Ditto

 Bean 1FL overview

 Capping cracked to Bean 1FL window BE.EW.01.08- HCL to address

 Capping 1FL Bean arcade adjacent Cunliffe- gap formed between two

 Ditto- cutaway required. HCL to ensure DPC lapped up

 Beam decoration required- Action HCL

Ditto- CVA to confirm colour

 Cunliffe 1FL- bulkhead projects due to electrical services- CVA request that this be brought in line with column projecting adjacent and shallower bulkhead continued above.- Action HCL

 Bead now installed 2FL where wobbly plaster line- Cunliffe

 Cunliffe dormer- window installed in correct position. Stud and linings to be amended accordingly- Action HCL
 Ditto



 Awaiting link glazing following scaffold strike

 Soakaway installed- library square


Bean scaffold struck- clean down/ making good to follow- Action HCL