Site Visit 30.03.15

 Temporary power supplies built into acoustic rated wall

 Ramp/ slab not built as CVA dwgs- height of ducting/ height of fan coil unit to be reviewed in Link display joinery

 
 Cunliffe 1FL- Mist coat applied to soffit. Awaiting dot and dab boarding to external walls

 Ditto

 Making good still required to underside of slab 1FL Cunliffe refurb

 Repair to slab still required 1FL Cunliffe new build

 Bulkheads to Cunliffe 1FL- flangless grilles installed- awaiting skim coat

 Bean LRC overview

 Arches to arcade north elevation. Formwork reinstalled for arch rebuild

 Pointing underway to brickshield under link- Cunliffe

 HCL to confirm build up to metsec/ awnings if secondary steelwork omitted

Corbelled brickwork to gables Cunliffe south elevation

 Snots to be removed/ cill brickwork adjusted Cunliffe 2nd floor windows south elevation

 Cappings all installed without movement joints Cunliffe south elevation- refer elevations/ details/ specification

 Ditto

 Cappings installed projecting 35mm not as CVA details. Inconsistencies to underside. HCL to advise how this detail will be addressed. Action HCL

Lining to insitu infill GFL Bean Hall to be changed to MDF to allow swifter completion. COI to confirm. Action HCL