Ramp/ slab not built as CVA dwgs- height of ducting/ height of fan coil unit to be reviewed in Link display joinery
Ditto
Making good still required to underside of slab 1FL Cunliffe refurb
Repair to slab still required 1FL Cunliffe new build
Bulkheads to Cunliffe 1FL- flangless grilles installed- awaiting skim coat
Bean LRC overview
Arches to arcade north elevation. Formwork reinstalled for arch rebuild
Pointing underway to brickshield under link- Cunliffe
HCL to confirm build up to metsec/ awnings if secondary steelwork omitted
Corbelled brickwork to gables Cunliffe south elevation
Snots to be removed/ cill brickwork adjusted Cunliffe 2nd floor windows south elevation
Cappings all installed without movement joints Cunliffe south elevation- refer elevations/ details/ specification
Ditto
Cappings installed projecting 35mm not as CVA details. Inconsistencies to underside. HCL to advise how this detail will be addressed. Action HCL
Lining to insitu infill GFL Bean Hall to be changed to MDF to allow swifter completion. COI to confirm. Action HCL